K-RERA · the public record
ADONIA
· VegaCourtYard
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 16 Jul 2026Progress & dates
The timeline on file.
Promoter-reported construction
K-RERA quarterly filings · Q3 2025 to Q4 2025
declared completion
Not recorded
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 16 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1268/378/PR/181025/008183
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Approved plan number | 26/2024-25 | Use this to match the sanctioned drawing set shown by the builder. |
| Plan approval date | 01-03-2025 | |
| Project start date | 01-07-2025 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filing⚠ 1 litigation case on record
- Injunction Suit — Principal Senior Civil Judge & CJM Mysuru (2025)
5 of 20 compliance document slots are filed as Not Applicable; the remaining 15 slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
⚠ Registration validity has lapsed: originally due 15 Jul 2026 — which has passed with no OC on file.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
Statutory approval status
RERA filingClean approvals profile: every applicable statutory NOC is on file. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC, environmental clearance and pollution-control clearance (KSPCB) are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.
9 further authority slots are marked not applicable by the regulator.
| Authority / NOC | Status | Date | File |
|---|---|---|---|
| Water supply and sewage board | Approved | 12-05-2025 | NOC - Water.pdf |
| KPTCL- BESCOM | Approved | 12-09-2025 | NOC - CESC.pdf |
Project team & certifications
RERA filingK-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Chartered accountant | Parimal Prasad P | 209074 | 2000 | Bengaluru Urban, Karnataka - 560004 |
| Engineer | Karthikeyan B | M-1796776 | 2023 | Bengaluru Urban, Karnataka - 560016 |
Financials & Construction Progress
Financial disclosures
RERA filingLatest quarterly filing (2025-Q4): ₹0.63 Cr collected from buyers, ₹0.42 Cr withdrawn from the project's escrow account.
| Construction progress | 75% → 100% (+25 pts) |
| Buyer collections in available QPRs | ₹0.68 Cr |
| Escrow withdrawals in available QPRs | ₹0.45 Cr (0.65x collections) |
- Construction progress moved from 75% to 100% across the filed QPR window.
- The builder has drawn 0.65x of buyer collections from escrow (about 65% of the ₹1 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.
QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.
The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.
RERA 70% project account is on file: HDFC. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Location & Connectivity
The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| MG Road / city centre | 3 km |
| Outer Ring Road / Manyata | 10 km |
| Bellandur–Marathahalli belt | 12 km |
| Electronic City | 16 km |
| Whitefield IT hub | 19 km |
| Kempegowda Int'l Airport | 30 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.