ANAHATA PHASE - 2

Hosakote · ISHTIKA VIBRANIUM DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

20%construction reportedQ1 2026 filing
99units not bookedof 181 · Q1 2026 filing
31 Jul 2029declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Jul 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2 BHK
26
3 BHK
78
2.5 BHK
77

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.0registered acres

90.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/304/PR/050725/007898

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 July 2029
Land area8,058 sq m (2.0 acres)
Homes registered181
Tower/wing entries2
Unit mix26 × 2 BHK, 78 × 3 BHK, 77 × 2.5 BHK

In context

Density90.9 homes per acre
Density in context73rd percentile of 112 Hosakote projects (median 79.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units181Total inventory registered with K-RERA.
Official carpet area15,939 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area23,466 sqmUseful scale context when comparing density and project cost.
Registered land area8,058 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.49Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)181Separate filed counts; these categories may overlap and are not added together.
Covered-parking field199Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberSTRRPA/TP/CC/314/2024-25Use this to match the sanctioned drawing set shown by the builder.
Plan approval date12-03-2025
Project start date01-08-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 BHK2614%1,674 sqm
3 BHK7843%7,615 sqm
2.5 BHK7743%6,650 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower A12777744.8 m
Tower B1210410444.8 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 181 official flat/unit rows, matching the 181 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK7895.0-99.7 sqm48.1-52.3 sqm78
2.5 BHK7783.2-88.2 sqm45.0-47.4 sqm77
2 BHK2664.4 sqm35.3-35.6 sqm26

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower B10464.4-99.2 sqm35.3-51.2 sqm104
Tower A7783.2-99.7 sqm45.8-52.3 sqm77
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
AG01Tower A02.5 BHK85.9 sqm46.3 sqm1
AG03Tower A02.5 BHK83.2 sqm45.8 sqm1
AG04Tower A03 BHK99.7 sqm52.3 sqm1
AG05Tower A03 BHK96.4 sqm49.7 sqm1
AG06Tower A03 BHK97.4 sqm48.1 sqm1
A101Tower A12.5 BHK85.9 sqm46.3 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

1 of 25 compliance document slots are filed as Not Applicable; the remaining 24 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantA B Yerriswamy2235262009Ballari, Karnataka - 583103
EngineerMandhadi Venkataramana ReddyBCCL/BL 3.6/E-0011/22 231990Bengaluru Urban, Karnataka - 560043
ArchitectT V SrinnivasCA/97/218981990Hyderabad, Telangana - 500044
ContractorISHTIKA VIBRANIUM DEVELOPERS LLP-2024Bengaluru Urban, Karnataka - 560078

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹8.20 Cr collected from buyers, ₹5.89 Cr withdrawn from the project's escrow account.

Construction progress5% → 20% (+15 pts)
Units sold/booked as registered82/181 (45%)
Buyer collections in available QPRs₹26.69 Cr
Escrow withdrawals in available QPRs₹17.77 Cr (0.67x collections)
  • Construction progress moved from 5% to 20% across the filed QPR window.
  • The builder has drawn 0.67x of buyer collections from escrow (about 67% of the ₹27 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹50.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC 2nd Phase JP Nagar IFSC Code : HDFC0004140 Pin Code : 560078. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub5 km
Bellandur–Marathahalli belt13 km
Outer Ring Road / Manyata20 km
MG Road / city centre20 km
Electronic City21 km
Kempegowda Int'l Airport26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Ishtika Vibranium.
Ishtika Vibranium has 2 projects registered in Bangalore.

Other projects by this builder in Bangalore

Anahata
On track · 30% built · 46% sold

Other RERA-registered projects in M V Extenstion

Major developers building in M V Extenstion

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.