04 Feb 2021declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

04 Feb 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

13.6registered acres

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/304/PR/190305/002479

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion4 February 2021
Land area55,214 sq m (13.6 acres)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered land area55,214 sqmThe land area attached to this K-RERA registration.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date05-02-2019

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

16 of 37 compliance document slots are filed as Not Applicable; the remaining 21 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 04 Feb 2021, extended (Covid Extension) to 04 Nov 2021 — both dates have passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (26 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
DILIP KUMAR BEHERA vs M/S.S.L.RESIDENTIAL LAYOUTRefund of amount with interestAUTHORITY24/02/2026
Alok Nath Upadhyay & Rashmi Upadhyay vs SL RESIDENTIAL LAYOUT PVT LTDInterest on delay period from the date of Rera completion date (including grace period) till the time we get registration done.AUTHORITY22/11/2024
M MONOJ KUMAR vs SL RESIDENTIAL LAYOUT PVT LTDInterest on delay period from the date of RERA completion date (including grace period) till the time we get registration done.AUTHORITY22/11/2024
Balakrishna Yerabatta vs SL RESIDENTIAL LAYOUT PVT LTDLand Registration should be done within 3months or else requesting RERA to relief me refund the amount paid along with compensation from developer.AUTHORITY22/07/2025
KUMAR SHITANSHU vs M/S.S.L.RESIDENTIALInterest on the delay period from the date of intimation of registration (April 2022) until the time the registration is completed or Refund the amount paid along with compensation.AUTHORITY21/04/2026
Varsha Priyadarshini & Rajesh Kumar Verma vs SL RESIDENTIAL LAYOUT PVT LTDInterest on delay period from the date of Rera completion date (including grace period) till the time we get registration done.AUTHORITY20/12/2024
SIMRAN UPADHYAY vs SL RESIDENTIAL LAYOUT PVT LTDINTEREST ON DELAY PERIODAUTHORITY20/12/2024
Ravi Shankar & Pooja Pandey vs SL RESIDENTIAL LAYOUT PVT LTDInterest on delay period from the date of rera completion date(including grace period) till the time we get the registration done.AUTHORITY20/12/2024
Venkatesulu P & Anitha M vs SL RESIDENTIAL LAYOUT PVT LTDInterest for the time between the rera completion date, including grace period and the date of registration completion.AUTHORITY20/12/2024
Bodeppagari Subramanyam vs SL RESIDENTIAL LAYOUT PVT LTDInterest for the time between the rera completion date, including grace period and the date of registration completion.AUTHORITY20/12/2024
Sonia Kad vs S L RESIDENTIAL LAYOUT PRIVATE LIMITEDCompensation basis 18% P.A for the delay on project delivery i.e from June 2021 till the time we get registration done. i.e on INR 41,44,895.AUTHORITY20/07/2023
Jeeson Santhosh Colaco vs SL Residential Layout Pvt LtdRefund of the amound paid and the Compensation on the incured lossAUTHORITY19/11/2024
Desanur Naveen Reddy vs SL RESIDENTIAL LAYOUT PVT LTDRegulatory Authority is requested to issue directions to the Respondent to return the sum of 24,70,100/- paid by the Complainant along with 18 percent interest per annum.AUTHORITY19/11/2024
M R PRADEEP vs SL RESIDENTIAL LAYOUTDIRECTION TO THE BUILDER/RESPONDENT TO REFUND THE ENTIRE AMOUNT WITH INTEREST THEREON ALONG WITH COMPENSATIONAUTHORITY19/02/2025
Abhishek Dwivedi vs SL. Residential Layout Pvt.LtdRefund of complete booking amount i.e. Rs 50,000 along with monitory compensation for the delayed period which as on date is 6 months & Rs 1000 which has been spent for registering this complaintAUTHORITY18/10/2022
Archana Valsan vs sl residential layout pvt ltdRefund(Principal +Interest) from Promoter/Builder for delayed possession of Plot at the Shriram Bageshri ProjectAUTHORITY16/09/2026
M Jayakumar vs SL Residential Layout Pvt LtdTo refund/pay the entire amount Rs.33,41,900/- together with interest at 18% PA from the date of receipt of said amounts, and the penalty/compensation of Rs.20,00,000/-AUTHORITY13/05/2024
KAMALNATH S REDDY & SUNITHA A vs SL RESIDENTIAL LAYOUT PVT LTDDIRECTION TO THE BUILDER/RESPONDENT TO REFUND THE ENTIRE AMOUNT WITH INTEREST THEREON ALONG WITH COMPENSATIONAUTHORITY13/05/2024
NANDANAVANAM VENKATESWARA RAO vs SL RESIDENTIAL LAYOUT PVT LTDDIRECT THE BUILDER/RESPONDENT TO REFUND THE ENTIRE AMOUNT TOGETHER WITH INTEREST THEREON AND COMPENSAITONAUTHORITY13/05/2024
ANKUR BANGA vs SL RESIDENTIAL LAYOUT PVT LTDDIRECTION TO THE BUILDER TO REFUND THE ENTIRE COST OF SALE TOGETHER WITH DEVELOPMENT CHARGES AND REGN EXPENSES THEREON ALONG WITH INTEREST THEREON AND COMPENSATION AS PER PROVISIONS OF RERAAUTHORITY13/05/2024
HARISH SOMANCHI & MINAKSHI ARAVINDA POCHANAPEDDI vs SL RESIDENTIAL LAYOUT PVT LTDDIRECTION TO THE BUILDER TO REFUND THE ENTIRE COST OF SALE TOGETHER WITH DEVELOPMENT CHARGES AND REGN EXPENSES THEREON ALONG WITH INTEREST THEREON AND COMPENSATION AS PER PROVISIONS OF RERAAUTHORITY13/05/2024
Mr. Shivakumara Y L & Mrs. Bhargavi B N vs S L Residential Layout Pvt LtdSeeking Refund of Rs.1,00,000/- along with compensation from the date of receipt of amount and any other action against the defendants at the descretion of the AuthorityAUTHORITY13/02/2023
Archana Valsan vs SL. Residential Layout Pvt.LtdRefund(Principal +Interest-18% p.a.) from Promoter/Builder for delayed possession of Plot at the Shriram Bageshri ProjectAUTHORITY10/07/2026
SONIA KAD vs Shriram BageshriDIRECTION TO THE BUILDER TO REFUND THE ENTIRE COST OF SALE TOGETHER WITH DEVELOPMENT CHARGES AND REGN EXPENSES THEREON ALONG WITH INTEREST THEREONAUTHORITY06/04/2026
Achu Raj vs M/S S L RESIDENTIAL LAYOUT PRIVATE LIMITEDRefund of the amount along with the interestAUTHORITY02/01/2024
PRASANTH S vs S.L.RESIDENTIAL LAYOUT PVT LTDRequesting a refund of the payments done with interest.AUTHORITY01/12/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (9 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/200611/0006010
11-06-2020
Delay In Refund Of Pre-Agreement Booking Amount Against Cancelled Plot BookingShriram BageshriDISPOSED AUTHORITY BENCH5
CMP/200723/0006175
23-07-2020
SEEKING REFUND AND COMPENSATIONSHRIRAM BAGESHRIDISPOSED AUTHORITY BENCH5
CMP/211113/0008551
13-11-2021
Complaint Against SL. Residential Layout Pvt.Ltd (Project Shriram Bageshri)Shriram BageshriDISPOSED AUTHORITY BENCH6
CMP/220321/0009196
21-03-2022
No update on the Registration/delivery of project and no update on the compensation for delay.Shriram BageshriDISPOSED AUTHORITY BENCH6
CMP/221025/0010132
25-10-2022
Refund of the amount paidShriram BageshriDISPOSED AUTHORITY BENCH6
CMP/221221/0010498
21-12-2022
INVALID SALE DEED CONSEQUENT TO THE CANCELLATION OF LAYOUT PLAN APPROVALShriram BageshriDISPOSED AUTHORITY BENCH6
CMP/221221/0010499
21-12-2022
INVALID SALE DEED CONSEQUENT TO THE CANCELLATION OF LAYOUT PLAN APPROVALShriram BageshriDISPOSED AUTHORITY BENCH6
CMP/221226/0010521
26-12-2022
NON COMPLIANCE OF SALE AGREEMENT AND NON EXECUTION OF SALE DEEDShriram BageshriDISPOSED AUTHORITY BENCH6

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: Axis Bank sector 5 nerul navi mumbai (IFSC UTIB0003335, a/c …8365). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub9 km
Bellandur–Marathahalli belt16 km
Outer Ring Road / Manyata19 km
Kempegowda Int'l Airport20 km
MG Road / city centre21 km
Electronic City26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sl Residential.

Other RERA-registered projects in M V Extenstion

Major developers building in M V Extenstion

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Shriram Bageshri?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026