RERA Property Intelligence Report · Preview

BIRLA APPLE AROMA

APPLE SPIRE INDIA · Bengaluru South · K-RERA PRM/KA/RERA/1251/310/PR/171125/000383

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

180
Registered units
₹69.0 Cr
Est. construction cost
Units profiled
29
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units180Total inventory registered with K-RERA.
Official carpet area17,986 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area9,191 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.49Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings2Official tower/wing count in the K-RERA detail page.
Parking disclosed197 total (0 open) — 1.09 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date15-04-2016

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
RESIDENTIAL APARTMENTS172100%17,986 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower A149098-
Tower B149099-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 180 official flat/unit rows, matching the 180 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK1208.0-122.0 sqm50.7-53.6 sqm120
2.5BHK5810.0-106.7 sqm44.7-46.9 sqm58
1BHK263.5-70.8 sqm27.9-31.1 sqm0 (2 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower A908.0-122.0 sqm27.9-53.6 sqm89 (1 with 0)
Tower B908.0-122.0 sqm31.1-53.6 sqm89 (1 with 0)
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A001Tower A03BHK121.6 sqm53.4 sqm1
A002Tower A03BHK122.0 sqm53.6 sqm1
A003Tower A02.5BHK103.2 sqm45.3 sqm1
A004Tower A03BHK115.6 sqm50.8 sqm1
A005Tower A03BHK115.5 sqm50.7 sqm1
A006Tower A01BHK63.5 sqm27.9 sqm0

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~257 sqft — compact homes (1–2BHK / studio territory), not compact stock. This is a mid-scale project — 180 homes across 2 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 197 parking spaces for 180 homes (~1.1 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~50 sqm per home; across all 180 homes that is ~98% of the plot — a healthy sign: buyers collectively hold close to all the land. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 25 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Mar 2019, extended (Extension) to 31 Mar 2026 — both dates have passed with no OC on file. The extension on file was granted on 11 Jul 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/310/PR/220711/000383) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

1 K-RERA order on this project (PROJECT EXTENSION) — read the order copies on the K-RERA portal.

K-RERA complaint orders (12 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Raghavendra P Joshi vs BIRLA APPLE AROMAComplete Development work; Secure Extension of Project; To Pay Delay Period Interest; Register Sale deed and hand over vacant Possession of Flat.AUTHORITY23/07/2024
Hrishikesh Kulkarni vs BIRLA APPLE AROMAdirecting the Respondent to complete the Development work, directing the Respondent to register the sale Deed, directions tothe Respondent to secure extension, directing builder to pay delay interestAUTHORITY21/04/2026
Puneeth P vs APPLE SPIRE INDIA LLPa)Pass Judgement and decree directing the Respondent to complete the Development work of the Schedule ‘D’ property. b)Pass judgement and decree directing the Respondent to register the sale Deed of tAUTHORITY18/04/2026
Sainath Seshadri Iyengar vs APPLE SPIRE INDIA LLPdirecting the Respondent to complete the Development work, directing the Respondent to register the sale Deed, directions tothe Respondent to secure extension, directing builder to pay delay interestAUTHORITY18/04/2026
Krishna Prahalad Bindiganavale vs BIRLA APPLE AROMAdirecting the Respondent to complete the Development work, directing the Respondent to register the sale Deed, directions tothe Respondent to secure extension, directing builder to pay delay interestAUTHORITY18/04/2026
Sri Shivakumar Dharmalingam vs APPLE SPIRE INDIA LLPa. Pass an order directing the Respondent to complete the construction work of the said project and to hand over the said flat., Pass an order directing the Respondent to register the sale deedAUTHORITY18/04/2026
Lokanatha Rao vs APPLE SPIRE INDIA LLPdirecting the Respondent to complete the Development work, directing the Respondent to register the sale Deed,directions tothe Respondent to secure extension, directing builder to pay delay interestAUTHORITY16/04/2026
Prashant Shetty vs APPLE SPIRE INDIA LLPdirecting the Respondent to complete the Development work, directing the Respondent to register the sale Deed, directions tothe Respondent to secure extension, directing builder to pay delay interestAUTHORITY16/04/2026
Arunkumar C Hullamani vs APPLE SPIRE INDIA LLPdirecting the Respondent to complete the Development work, directing the Respondent to register the sale Deed, directions tothe Respondent to secure extension, directing builder to pay delay interestAUTHORITY16/04/2026
Prakriti Govil vs Apple Spire India Llpdirecting the Respondent to complete the Development work, directing the Respondent to register the sale Deed, directions to the Respondent to secure extension, directing builder to pay delay interestAUTHORITY15/04/2026
Prashant Odugoudar vs Apple Spire India Pvt LtdComplete project, handover the property, execute sale deed, pay delay period interestAUTHORITY15/04/2026
Pramod Kulkarni vs BIRLA APPLE AROMAComplete Development work; Secure Extension of Project; To Pay Delay Period Interest; Register Sale deed and hand over vacant Possession of FlatAUTHORITY05/08/2024

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (2 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/210618/0008012
18-06-2021
WRONG ASSURANCES AS TO SIZE OF THE FLAT AND POSSESSION DATE.BIRLA APPLE SPIRE (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/201003/0006749
03-10-2020
Delayed project and expect complete refund immediatelyBIRLA APPLE SPIRE (another project by this promoter)DISPOSED AUTHORITY BENCH6

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved10-04-2015BWSSB (1) 10 04 2015.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved11-12-2014KSPCB NOC 11 12 2014.pdf
KPTCL- BESCOMApproved17-09-2014BESCOM 17 09 2014.pdf
Fire and SafetyApproved09-11-2024Fire NOC 19 11 2024.pdf
Airport Authority of IndiaApproved14-10-2014AA 14 10 2014.pdf
BSNL/Telecommunication DepartmentApproved14-10-2014BSNL 14 10 2014.pdf

Project team & certifications

RERA filing

K-RERA names 1 project professional/vendor row across Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ContractorSTARWORTH INFRASTRUCTURE & CONSTRUCTION LTD-2008no.39 ulsoor road, bangalore

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹2.79 Cr collected from buyers, ₹8.52 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹8.52 Cr) exceeded buyer collections (₹2.79 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress93% → 100% (+7 pts)
Units sold/booked as registered0/180 (0%)
Buyer collections in available QPRs₹5.50 Cr
Escrow withdrawals in available QPRs₹12.18 Cr (2.22x collections)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹38.3 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Fort (IFSC HDFC0000060, a/c …7942). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Electronic City11 km
MG Road / city centre12 km
Bellandur–Marathahalli belt15 km
Outer Ring Road / Manyata20 km
Whitefield IT hub23 km
Kempegowda Int'l Airport39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Apple Spire.
Apple Spire has 2 projects registered in Bangalore, 1 completed.

Other projects by this builder in Bangalore

Other RERA-registered projects in Anjanapura Township

Major developers building in Anjanapura Township

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Birla Apple Aroma?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 27 Jul 2026