Brigade Senate 1 (Wing 2)

Bengaluru North · Brigade Enterprises

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2022declared completionK-RERA registration · read 20 Sep 2026
44registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

COMMERCIAL
1
COMMERCIAL
1
COMMERCIAL
1
COMMERCIAL
7

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.2registered acres

37.4registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/309/PR/260522/004923

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 September 2022
Land area4,765 sq m (1.2 acres)
Units registered44
Tower/wing entries1
Unit mix10 × COMMERCIAL

In context

Density37.4 units per acre
Density in context16th percentile of 525 Bengaluru North projects (median 75.4)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units44Total inventory registered with K-RERA.
Official carpet area8,861 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area16,901 sqmUseful scale context when comparing density and project cost.
Registered land area4,765 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.84Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)247Separate filed counts; these categories may overlap and are not added together.
Covered-parking field229Separate filed counts; these categories may overlap and are not added together.
Open-parking field18Separate filed counts; these categories may overlap and are not added together.
Garage field247Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/Addl.Dir/JDNORTH/0074/19-20Use this to match the sanctioned drawing set shown by the builder.
Plan approval date04-03-2021
Project start date18-11-2020

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
COMMERCIAL110%489 sqm
COMMERCIAL110%873 sqm
COMMERCIAL110%287 sqm
COMMERCIAL770%915 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Brigade Senate 1 (Wing 2)94424739.9 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 44 official flat/unit rows, matching the 44 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
COMMERCIAL44129.4-287.0 sqm77.9-153.4 sqm185

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Brigade Senate 1 (Wing 2)44129.4-287.0 sqm77.9-153.4 sqm185
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
OFFICE - 001Brigade Senate 1 (Wing 2)0COMMERCIAL287.0 sqm153.4 sqm6
OFFICE - 101Brigade Senate 1 (Wing 2)1COMMERCIAL165.7 sqm107.0 sqm4
OFFICE - 102Brigade Senate 1 (Wing 2)1COMMERCIAL152.1 sqm99.6 sqm4
OFFICE - 104Brigade Senate 1 (Wing 2)1COMMERCIAL170.7 sqm110.6 sqm4
OFFICE - 201Brigade Senate 1 (Wing 2)2COMMERCIAL168.5 sqm101.6 sqm4
OFFICE - 202Brigade Senate 1 (Wing 2)2COMMERCIAL143.3 sqm86.8 sqm3

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

14 of 45 compliance document slots are filed as Not Applicable; the remaining 31 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Sep 2022 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Complaints on this project's K-RERA page (21 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190802/0003774
02-08-2019
Project delay compensation & Veracity of the agreement & Brochure while bookingBrigade Panorama (another project by this promoter)DISPOSED AO
CMP/190915/0004196
15-09-2019
Waiting period more than 1.5 years, amenities built on kharab land, Club house not as per agreementBrigade Panorama (another project by this promoter)DISPOSED AO
CMP/190920/0004245
20-09-2019
Delay in paying the Delay CompensationBrigade Panorama (another project by this promoter)DISPOSED AO
CMP/200211/0005414
11-02-2020
Brigade group not given the compensation as per RERA and changes in the layout planBrigade Panorama (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/200513/0005880
13-05-2020
Refund of amount due to delay in registration/handoverBrigade Panorama (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/201130/0007159
30-11-2020
Brigade has backed out of delay compensation payment after earlier assuring to pay the sameBrigade Panorama (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/210212/0007498
12-02-2021
Recovery of delay compensation, rental loss & Property tax amount with Interest for 6 years of delay caused by builder to deliver possession of flatPlumeria Lifestyle at Brigade Meadows (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/210512/0007948
12-05-2021
BUILDER NOT ALLOWING INSPECTION OF OUR APARTMENTBrigade Buena Vista-Phase 2 (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantT.RAMACHANDRAN AND CO.,009009S2020Bengaluru Urban, Karnataka - 560003
EngineerSterling Engineering Consultancy Services Pvt LtdBCCL/BL-3.6/SE-0103/21-221983Bengaluru Urban, Karnataka - 560025
ArchitectGauri GoreCA/2011/529421998Bengaluru Urban, Karnataka - 560001
ContractorM/s. JMC Projects (India) Ltd.-1986Bengaluru Urban, Karnataka - 560025

Builder track record

RERA filing

Brigade has 60 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Brigade Enterprises”) (average reported construction progress 70%). 30 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹108.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: KOTAK MAHINDRA BANK M.G Road IFSC Code : KKBK0008066 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata4 km
MG Road / city centre9 km
Bellandur–Marathahalli belt17 km
Whitefield IT hub20 km
Kempegowda Int'l Airport22 km
Electronic City24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Brigade Enterprises. View Brigade Enterprises's full track record →
Brigade Enterprises has 49 projects registered in Bangalore, 9 completed.

Other projects by this builder in Bangalore

Brigade Laguna
Filing overdue · 100% built · 100% sold
Brigade Oak Tree Place
Filing overdue · 100% built
Pearl At Brigade Atmosphere
Filing overdue · 100% built · 100% sold
Azalea At Brigade Meadows
No filings
Brigade Komarla Heights
On track · 100% built · 100% sold
Brigade Nanda Heights
On track · 100% built · 99% sold

Other RERA-registered projects in R.M.V. 2nd Stage

Major developers building in R.M.V. 2nd Stage

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.