Bangalore/Project record

K-RERA · the public record

CHARTERED GULMOHAR

Nelamangala · CHARTERED HOUSING

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

5%construction reportedQ1 2026 filing
30 Sep 2028declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q4 2025 to Q1 2026

declared completion

30 Sep 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/307/PR/110226/008465

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 September 2028

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Approved plan number60/2025-26Use this to match the sanctioned drawing set shown by the builder.
Plan approval date23-01-2026
Project start date02-03-2026

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

1 of 23 compliance document slots are filed as Not Applicable; the remaining 22 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (NOC from ESCOMs)
Water & sewage (BWSSB/KWSSB)✓ On file (NOC for Water)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB (If Applicable))
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (1 complaint listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/221105/0010186
05-11-2022
Private Garden not allocatedChartered Hummingbird (another project by this promoter)DISPOSED AUTHORITY BENCH5

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

3 of 5 applicable approvals are on file; still outstanding: Engineering Department (PWD) for completion of development works and Horticulture department. Confirm each has been granted, not merely applied for, before booking.

6 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved06-02-2026Panchayath NOC- Water.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved09-10-2025KSPCB NOC.pdf
Engineering Department (PWD) for completion of development worksTo Be Applied-View NOC
KPTCL- BESCOMApproved24-09-2025BESCOM NOC.pdf
Horticulture departmentTo Be Applied-View NOC

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantUDAY KUMAR HEGDE0185931981Bengaluru Urban, Karnataka - 560003
EngineerC.G KUMARBCC/BL-3.6/SE-0349/19-202019Bengaluru Rural, Karnataka - 560090

Builder track record

RERA filing

Chartered Housing has 4 other K-RERA-registered projects in our records (average reported construction progress 80%). 3 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹3.96 Cr collected from buyers, ₹2.73 Cr withdrawn from the project's escrow account.

Construction progress4% → 5% (+1 pts)
Buyer collections in available QPRs₹5.06 Cr
Escrow withdrawals in available QPRs₹2.73 Cr (0.54x collections)
  • Construction progress moved from 4% to 5% across the filed QPR window.
  • The builder has drawn 0.54x of buyer collections from escrow (about 54% of the ₹5 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: Bank of Baroda Victoria Road IFSC Code : BARB0VJVICT Pin Code : 560047. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~27 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Outer Ring Road / Manyata27 km
MG Road / city centre30 km
Kempegowda Int'l Airport32 km
Bellandur–Marathahalli belt40 km
Whitefield IT hub43 km
Electronic City45 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Chartered Housing. View Chartered Housing's full track record →
Chartered Housing has 5 projects registered in Bangalore.
2 complaints on the K-RERA register against Chartered Housing in Bangalore.

Other projects by this builder in Bangalore

Chartered 1956
On track · 80% built · 14% sold
Chartered Windsong - 2
No filings

Other RERA-registered projects in Annappacharya

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.