Green Groves

Nelamangala · SATTVA INFRASTRUCTURE INDIA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ1 2026 filing
17 Sep 2026declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

17 Sep 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

9.14M X 15.24M
153

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/307/PR/040524/006863

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion17 September 2026
Unit mix153 × 9.14M X 15.24M

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Approved plan number51/2019-2020Use this to match the sanctioned drawing set shown by the builder.
Plan approval date13-01-2022
Project start date01-03-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
9.14M X 15.24M153100%0 sqm

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

⚠ 1 litigation case on record

  • Original Suit — II - Additional Senior Civil Judge , Nelamangala (2021)

22 of 47 compliance document slots are filed as Not Applicable; the remaining 25 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 17 Sep 2026 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (2 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Shamanth kumar vs M/S.SATTVA INFRASTRUCTUREREFUND FULL AMOUNT FROM THE BUILDERAUTHORITY24/08/2026
S NAGARAJI vs M/s.Sattva InfrastructureRectification of the Draft Agreement: RERA may pass an order mandating the inclusion of the pendency of Suit No. OS 631/2021 in the draft agreement and sale deedAUTHORITY09/06/2026

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC and environmental clearance are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

8 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved26-06-2019NelamangalaWater NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved28-03-2024NelamangalaCFE.pdf
KPTCL- BESCOMApproved29-06-2022NelamangalaBESCOM NOC (1).pdf

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantM O J & ASSOCIATES015425S2014Bengaluru Urban, Karnataka - 560025
EngineerSRIDHAR M CBCCL/BL-3.6 SE-158/2014-20151992Bengaluru Urban, Karnataka - 560024

Builder track record

RERA filing

Sattva has 23 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Sattva Infrastructure”) (average reported construction progress 34%). 10 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹31.76 Cr collected from buyers, ₹5.25 Cr withdrawn from the project's escrow account.

Construction progress83% → 100% (+17 pts)
Buyer collections in available QPRs₹110.24 Cr
Escrow withdrawals in available QPRs₹55.79 Cr (0.51x collections)
  • Construction progress moved from 83% to 100% across the filed QPR window.
  • The builder has drawn 0.51x of buyer collections from escrow (about 51% of the ₹110 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: Axis Bank. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~27 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Outer Ring Road / Manyata27 km
MG Road / city centre29 km
Kempegowda Int'l Airport36 km
Bellandur–Marathahalli belt39 km
Electronic City43 km
Whitefield IT hub43 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sattva Infrastructure. View Sattva Infrastructure's full track record →

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.