Bangalore/Project record

K-RERA · the public record

INDIRA RESIDENCY

· SHREE VIGNESHWARA DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

49%construction reportedQ1 2026 filing
15units not bookedof 28 · Q1 2026 filing
28registered unitsK-RERA registration · read 16 Jul 2026

The record · free to read

Registration read 16 Jul 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 16 Jul 2026

Inventory & scale

What this registration contains.

Residential Apartments
28

Filed categories, unchanged · K-RERA registration · read 16 Jul 2026

The whole registration

0.3registered acres

92.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1257/334/PR/300525/007801

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Land area1,227 sq m (0.3 acres)
Homes registered28
Tower/wing entries1
Unit mix28 × Residential Apartments

In context

Density92.3 homes per acre
Density in context62nd percentile of 4882 projects in this register (median 82.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units28Total inventory registered with K-RERA.
Official carpet area4,072 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area6,580 sqmUseful scale context when comparing density and project cost.
Registered land area1,227 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI4Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)72Separate filed counts; these categories may overlap and are not added together.
Covered-parking field61Separate filed counts; these categories may overlap and are not added together.
Open-parking field11Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberE9BA 20/2024-25 192178Use this to match the sanctioned drawing set shown by the builder.
Plan approval date26-11-2024
Project start date01-04-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Residential Apartments28100%4,072 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
INDIRA RESIDENCY14287244 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 28 official flat/unit rows, matching the 28 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK28125.5-147.0 sqm0.0-0.0 sqm56

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
INDIRA RESIDENCY28125.5-147.0 sqm0.0-0.0 sqm56
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
101INDIRA RESIDENCY13 BHK125.5 sqm0.0 sqm2
102INDIRA RESIDENCY13 BHK129.2 sqm0.0 sqm2
201INDIRA RESIDENCY23 BHK146.7 sqm0.0 sqm2
202INDIRA RESIDENCY23 BHK147.0 sqm0.0 sqm2
301INDIRA RESIDENCY33 BHK146.7 sqm0.0 sqm2
302INDIRA RESIDENCY33 BHK147.0 sqm0.0 sqm2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 23 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance and pollution-control clearance (KSPCB) are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

7 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved03-03-2025Annx 96 Water NOC.pdf
KPTCL- BESCOMApproved01-03-2025Annx 95 MESCOM NOC.pdf
Fire and SafetyApproved10-10-2024Annx 99 Fire NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantHarish Khetan0450122018Dakshina Kannada, Karnataka - 575006
EngineerKrishna ShettyMNG/BL/10941/23-242023Dakshina Kannada, Karnataka - 575004
ArchitectChaithanya K ShettyCA/2020/1263342020Dakshina Kannada, Karnataka - 575004
ContractorSHREE VIGNESHWARA DEVELOPERS-2012Dakshina Kannada, Karnataka - 575002

Builder track record

RERA filing

Shree Vigneshwara has 3 other K-RERA-registered projects in our records (average reported construction progress 77%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹5.20 Cr collected from buyers, ₹4.09 Cr withdrawn from the project's escrow account.

Construction progress35% → 49% (+14 pts)
Units sold/booked as registered13/28 (46%)
Buyer collections in available QPRs₹9.10 Cr
Escrow withdrawals in available QPRs₹9.53 Cr (1.05x collections)
  • Construction progress moved from 35% to 49% across the filed QPR window.
  • Across available QPR rows, escrow withdrawals are 1.05x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹75.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Bank of Baroda Bendoor IFSC Code : BARB0VJBEND Pin Code : 575002. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~303 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
MG Road / city centre301 km
Outer Ring Road / Manyata303 km
Electronic City307 km
Bellandur–Marathahalli belt309 km
Kempegowda Int'l Airport313 km
Whitefield IT hub316 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Shree Vigneshwara.
Shree Vigneshwara has 4 projects registered in Bangalore.

Other projects by this builder in Bangalore

Pushyaraga
On track · 77% built · 45% sold

Other RERA-registered projects in Kalyan Nagar

Major developers building in Kalyan Nagar

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.