Bangalore/Project record

K-RERA · the public record

JR ONE EAST

· JR Housing Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

93%construction reportedQ4 2025 filing
0registered unitsK-RERA registration · read 04 Jul 2026

The record · free to read

Registration read 04 Jul 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q4 2025

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 04 Jul 2026

Inventory & scale

What this registration contains.

Plotted Development
177

Filed categories, unchanged · K-RERA registration · read 04 Jul 2026

The whole registration

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/304/PR/161224/007298

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Unit mix177 × Plotted Development

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Approved plan numberPlanUse this to match the sanctioned drawing set shown by the builder.
Plan approval date06-01-2024
Project start date01-11-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Plotted Development177100%32,917 sqm

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 7 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

0 of 5 applicable approvals are on file; still outstanding: Water supply and sewage board, KSPCB- PCB (10 Acres to 125 Acres), Engineering Department (PWD) for completion of development works, KPTCL- BESCOM and Horticulture department. Pollution-control clearance (KSPCB) is among them — a high-importance clearance, so confirm it has been granted (not just applied for) before you book.

6 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardTo Be Applied-View NOC
KSPCB- PCB (10 Acres to 125 Acres)To Be Applied-View NOC
Engineering Department (PWD) for completion of development worksTo Be Applied-View NOC
KPTCL- BESCOMTo Be Applied-View NOC
Horticulture departmentTo Be Applied-View NOC

Builder track record

RERA filing

Jr Housing has 14 other K-RERA-registered projects in our records (average reported construction progress 99%). 9 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹34.06 Cr collected from buyers, ₹34.06 Cr withdrawn from the project's escrow account.

Construction progress88% → 93% (+5 pts)
Buyer collections in available QPRs₹40.91 Cr
Escrow withdrawals in available QPRs₹40.91 Cr (1.00x collections)
  • Construction progress moved from 88% to 93% across the filed QPR window.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: Branch : IFSC Code : Pin Code : IFSC Code : Pin Code :. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub10 km
Bellandur–Marathahalli belt16 km
Outer Ring Road / Manyata18 km
Kempegowda Int'l Airport19 km
MG Road / city centre21 km
Electronic City26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Jr Housing. View Jr Housing's full track record →
Jr Housing has 15 projects registered in Bangalore, 5 completed.

Other projects by this builder in Bangalore

JR Club Class
Filing overdue · 100% built
JR Eastfields
Filing overdue · 100% built
JR Queenstown
Filing overdue · 100% built
JR Strr Enclave
Filing overdue · 100% built
JR Garden Retreat Phase 3
No filings

Other RERA-registered projects in M V Extenstion

Major developers building in M V Extenstion

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.