Bangalore/Project record

K-RERA · the public record

KNS ANANTA PHASE II

Bengaluru South · KNS PROPWORTH

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ1 2026 filing
31 May 2028declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 May 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Plots (6.1 x 9.14 Meter)
38

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/100823/006137

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 May 2028
Unit mix38 × Plots (6.1 x 9.14 Meter)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Approved plan numberNo.BDA/TPM/PRL-45/2022-23/276/2023-24.Use this to match the sanctioned drawing set shown by the builder.
Plan approval date04-05-2023
Project start date31-05-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Plots (6.1 x 9.14 Meter)38100%2,118 sqm

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

24 of 42 compliance document slots are filed as Not Applicable; the remaining 18 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

0 of 2 applicable approvals are on file; still outstanding: Water supply and sewage board and KPTCL- BESCOM. Confirm each has been granted, not merely applied for, before booking.

9 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardTo Be Applied-View NOC
KPTCL- BESCOMTo Be Applied-View NOC

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantICHR & Associates2572482021Bengaluru Urban, Karnataka - 560003
EngineerER. RAJASHEKAR KAKAREDDI45/19/CE/0368/20092006Bengaluru Urban, Karnataka - 560094

Builder track record

RERA filing

Kns Propworth has 3 other K-RERA-registered projects in our records (average reported construction progress 53%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹2.61 Cr collected from buyers, ₹0.96 Cr withdrawn from the project's escrow account.

Construction progress95% → 100% (+5 pts)
Buyer collections in available QPRs₹9.28 Cr
Escrow withdrawals in available QPRs₹21.29 Cr (2.29x collections)
  • Construction progress moved from 95% to 100% across the filed QPR window.
  • Across available QPR rows, escrow withdrawals are 2.29x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: HDFC Richmond Road IFSC Code : HDFC0000523 Pin Code : 560025. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~23 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
MG Road / city centre19 km
Outer Ring Road / Manyata23 km
Electronic City27 km
Bellandur–Marathahalli belt27 km
Whitefield IT hub34 km
Kempegowda Int'l Airport41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Kns Propworth.
Kns Propworth has 4 projects registered in Bangalore, 2 completed.

Other projects by this builder in Bangalore

KNS Ananta
On track · 100% built
KNS Ananta Phase III
On track · 10% built
KNS Unnati Phase V
On track · 50% built

Other RERA-registered projects in Yeswanthpur

Major developers building in Yeswanthpur

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in KNS Ananta Phase II?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026