RERA Property Intelligence Report · Preview

KRSNA LABURNUM

Dr. K. Balaraman · Bengaluru North · K-RERA PRM/KA/RERA/1251/309/PR/171214/001226

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

Registered units
₹36.5 Cr
Est. construction cost
Units profiled
17
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Official carpet area2,500 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area2,793 sqmThe land area attached to this K-RERA registration.
Parking disclosed85 total (20 open)Confirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date10-02-2015

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
A2100%2,500 sqm

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 13 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 10 Aug 2018, extended (an extension) to 10 Aug 2019 — both dates have passed with no OC on file. An extension application filed on 10 Apr 2019 is pending with K-RERA — until it is approved, the registration stands lapsed.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (10 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
KRISHNAMRAJU vs KRSNA LABURNUMTo execute the Sale Deed in favour of the ComplainantAUTHORITY31/10/2022
Bojaraj T Shetty vs KRSNA LABURNUMTo execute the Sale Deed in favour of the ComplainantsAUTHORITY31/10/2022
VIMALA SHIVANANDA vs K .BALARAMANTo execute the Sale Deed in favour of the ComplainantAUTHORITY31/10/2022
HARISH vs DR. K. BALARAMANTo execute the Sale Deed in favour of the ComplainantAUTHORITY31/10/2022
SHIVARAMAKRISHNA GANAPATHI vs KRSNA LABURNUMTo execute the Sale Deed in favour of the ComplainantAUTHORITY31/10/2022
N J Babu vs Dr. K. BalaramanTo execute the Sale Deed in favour of the ComplainantAUTHORITY31/10/2022
Anupa Rajesh vs Dr. K. BalaramanTo execute the Sale Deed in favour of the ComplainantsAUTHORITY31/10/2022
Mr.ASHWIN Balakrishna vs K BALARAMANTo execute the Sale Deed in favour of the ComplainantAUTHORITY31/10/2022
Swathi Shetty vs KRSNA LABURNUMTo execute the Sale Deed in favour of the ComplainantAUTHORITY31/10/2022
B G Nalini vs Mr. K.BalaramanDelivery of possession and delay compensationAUTHORITY25/04/2024

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (13 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190215/0002143
15-02-2019
Failure to complete and deliver as agreedKRSNA LABURNUMDISPOSED AO
CMP/190215/0002149
15-02-2019
Failure to obtain sanctions and complete project on timeKRSNA LABURNUMDISPOSED AO
CMP/190223/0002259
23-02-2019
Failure to complete and deliver as agreedKRSNA LABURNUMDISPOSED AO
CMP/190225/0002283
25-02-2019
Failure to complete and deliver as agreedKRSNA LABURNUMDISPOSED AO
CMP/190326/0002521
26-03-2019
Failure to complete and deliver as agreedKRSNA LABURNUMDISPOSED AO
CMP/190416/0002672
16-04-2019
Compensation for the delay caused in handing over the possessionKRSNA LABURNUMDISPOSED AO
CMP/190416/0002673
16-04-2019
Compensation for the delay caused in handing over the possessionKRSNA LABURNUMDISPOSED AO
CMP/190917/0003607
17-09-2019
Breach of AgreementKRSNA LABURNUMDISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectDESIGN PLUS-2009GEDDALAHALLI, SANJAYNAGAR
ContractorFOCI INFRA TECH-2005NEAR KANNIKA PARMESHWARI TEMPLE, AMARJYOTHI LAYOUT SANJAYNAGAR
Structural engineerR.SYED KHADER---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: VIJAYA BANK VIJAYASAMRUDDHI (IFSC VIJB0001477, a/c …0033). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata6 km
MG Road / city centre8 km
Bellandur–Marathahalli belt17 km
Whitefield IT hub21 km
Kempegowda Int'l Airport23 km
Electronic City24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Dr Balaraman.
22 complaints on the K-RERA register against Dr Balaraman in Bangalore.

Other RERA-registered projects in R.M.V. 2nd Stage

Major developers building in R.M.V. 2nd Stage

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Krsna Laburnum?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 27 Jul 2026