MAHALASA CLASSIC

· MHALASA CONTRACTORS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

83%construction reportedQ1 2026 filing
36units not bookedof 36 · Q1 2026 filing
36registered unitsK-RERA registration · read 16 Jul 2026

The record · free to read

Registration read 16 Jul 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 16 Jul 2026

Inventory & scale

What this registration contains.

2 BHK
18
SHOP
2
3BHK
16

Filed categories, unchanged · K-RERA registration · read 16 Jul 2026

The whole registration

0.3registered acres

109.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1274/351/PR/300124/006583

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Land area1,328 sq m (0.3 acres)
Homes registered36
Tower/wing entries2
Unit mix18 × 2 BHK, 2 × SHOP, 16 × 3BHK

In context

Density109.7 homes per acre
Density in context77th percentile of 4882 projects in this register (median 82.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units36Total inventory registered with K-RERA.
Official carpet area2,177 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area3,864 sqmUseful scale context when comparing density and project cost.
Registered land area1,328 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.72Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)17Separate filed counts; these categories may overlap and are not added together.
Covered-parking field17Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberKWR-LBPAS-10697/22-23/BPUse this to match the sanctioned drawing set shown by the builder.
Plan approval date19-08-2023
Project start date15-01-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 BHK1850%1,223 sqm
SHOP26%16 sqm
3BHK1644%938 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
MAHALASA CLASSIC BLOCK A518814.45 m
MAHALASA CLASSIC BLOCK B518914.45 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 36 official flat/unit rows, matching the 36 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK1864.5-68.3 sqm2.4-3.4 sqm9 (9 with 0)
3 BHK1651.4-66.3 sqm2.5-3.3 sqm8 (8 with 0)
SHOP28.1-8.3 sqm0.5-0.5 sqm0 (2 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
MAHALASA CLASSIC BLOCK A1851.4-68.3 sqm2.4-3.4 sqm8 (10 with 0)
MAHALASA CLASSIC BLOCK B188.1-68.3 sqm0.5-3.4 sqm9 (9 with 0)
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1MAHALASA CLASSIC BLOCK A13 BHK65.2 sqm2.8 sqm1
2MAHALASA CLASSIC BLOCK A13 BHK63.6 sqm2.8 sqm1
101MAHALASA CLASSIC BLOCK A23 BHK53.2 sqm2.6 sqm0
102MAHALASA CLASSIC BLOCK A23 BHK51.4 sqm2.5 sqm0
103MAHALASA CLASSIC BLOCK A22 BHK68.3 sqm3.4 sqm1
104MAHALASA CLASSIC BLOCK A22 BHK68.1 sqm2.6 sqm0

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

6 of 29 compliance document slots are filed as Not Applicable; the remaining 23 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantRajesh Balkrishna Patange2474562019Belagavi, Karnataka - 590001
EngineerNAGESH VAMAN VERNEKARKWR-TL-5246/2016-171998Uttara Kannada, Karnataka - 581301
ArchitectGEETA NAGESH VERNEKARCA 94/168071996Uttara Kannada, Karnataka - 581301
ContractorMAHALASA CONTRACTORS-1998Uttara Kannada, Karnataka - 581301

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.00 Cr collected from buyers, ₹3.84 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹3.84 Cr) exceeded buyer collections (₹0.00 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress79% → 83% (+4 pts)
Units sold/booked as registered0/36 (0%)
Escrow withdrawals in available QPRs₹8.85 Cr
  • Construction progress moved from 79% to 83% across the filed QPR window.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹17.8 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Bank of Baroda KARWAR IFSC Code : BARB0VJKARW Pin Code : 581301. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~425 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Outer Ring Road / Manyata425 km
Kempegowda Int'l Airport426 km
MG Road / city centre428 km
Bellandur–Marathahalli belt437 km
Electronic City440 km
Whitefield IT hub442 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Mhalasa Contractors.

Other RERA-registered projects in Indiranagar

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.