RERA Property Intelligence Report · Preview

Mantri Webcity2B

Mantri Developers · Bengaluru South · K-RERA PRM/KA/RERA/1251/310/PR/171015/000620

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
8
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

441
Registered units
₹195.5 Cr
Est. construction cost
Units profiled
40
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units441Total inventory registered with K-RERA.
Registered land area21,448 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings3Official tower/wing count in the K-RERA detail page.
Parking disclosed481 total (24 open) — 1.09 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date04-03-2013

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
NOT WORKING00 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
K22147160-
L22147160-
M22147161-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 441 official flat/unit rows, matching the 441 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2.5-BHK23189.3-95.6 sqm5.4-5.9 sqm231
2-BHK21067.0-79.0 sqm4.1-4.9 sqm210

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
K14767.0-95.6 sqm4.2-5.9 sqm147
L14767.0-89.8 sqm4.1-5.5 sqm147
M14767.0-89.7 sqm4.1-5.4 sqm147
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
K-201K22.5-BHK89.3 sqm5.5 sqm1
K-202K22-BHK70.9 sqm4.4 sqm1
K-203K22-BHK70.9 sqm4.4 sqm1
K-204K22.5-BHK89.8 sqm5.5 sqm1
K-205K22-BHK78.1 sqm4.9 sqm1
K-206K22-BHK67.0 sqm4.2 sqm1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~870 sqft — mid-format homes (2–3BHK territory), not compact stock. This is a mid-scale project — 441 homes across 3 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 481 parking spaces for 441 homes (~1.1 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~5 sqm per home; across all 441 homes that is ~10% of the plot — on the lower side — the undivided shares sum to noticeably less than the plot, worth asking the builder why before relying on it. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

3 of 35 compliance document slots are filed as Not Applicable; the remaining 32 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Mar 2022, extended (Covid Extension) to 31 Dec 2022 — both dates have passed with no OC on file. An extension application filed on 02 Sep 2023 is pending with K-RERA — until it is approved, the registration stands lapsed.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

1 K-RERA order on this project (PROJECT EXTENSION) — read the order copies on the K-RERA portal.

K-RERA complaint orders (20 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Siva Prasad A K vs Mantri Developers Private LimitedAs prayed in the Facts of CaseAUTHORITY29/10/2022
RAKESH V. S vs MATRI DEVELOPER PVT. LTD.As prayed in factsAUTHORITY26/06/2023
GHATIGEPPA BASAVARAJ JAVALI vs MANTRI WEBCITY 2BAs prayed in the factsAUTHORITY24/05/2023
Gourav Gupta vs Mantri Developers Private LimitedInitiate penalty proceedings under Section 63 of the RERA Act against the Respondent Company and its DirectorsAUTHORITY24/03/2026
Debadatta patra vs mantri developers pvt ltdCancellation of my booking in the project and refund of entire amount along with interest from the builderAUTHORITY17/02/2023
Baskaran Kailasam vs MANTRI DEVELOPERS PVT LTDRegarding Cancellation Refund of Outstanding Amount with Interest for the Unit M603AUTHORITY16/01/2023
Jinu Raghavan vs MANTRI DEVELOPERS PVT LTDAs prayed in the Facts of ComplaintAUTHORITY15/10/2022
DEEPAK ABHICHANDANI vs MANTRI DEVELOPERS PVT LTDas prayed in the facts of caseAUTHORITY13/06/2023
Girish Nayak vs Mantri Technology Constellations Pvt LtdAs prayed in facts of ComplaintAUTHORITY07/11/2022
Srinivas Kulkarni vs Mantri Developers Private LimitedRequest you to help us get our money backAUTHORITY05/11/2022
Santosh Kumar Rout vs Mantri Developers Private LimitedA.Refund entire sale consideration, PRE-EMIs paid by Complainant along with 2x as promised under the Pre-EMI Scheme with Interest, B. Direct developer to pay loan outstanding amount.AUTHORITY03/06/2026
RAM SANTHANAM PRASAD & ANOTHER vs M/S MANTRI DEVELOPERS PRIVATE LIMITEDA.Refund entire sale consideration, PRE-EMIs paid by Complainant along with 2x as promised under the Pre-EMI Scheme with interest B. Direct developer to pay loan outstanding amountAUTHORITY03/04/2024
RAM SANTHANAM PRASAD & ANOTHER vs M/S MANTRI DEVELOPERS PRIVATE LIMITED: A.Refund entire sale consideration, PRE-EMIs paid by Complainant along with 2x as promised under the Pre-EMI Scheme with interest, B. Direct developer to pay loan outstanding amountAUTHORITY03/04/2024
ARVIND SANTHANAM PRASAD & ANOTHER vs M/S MANTRI DEVELOPERS PRIVATE LIMITEDA.Refund entire sale consideration, PRE-EMIs paid by Complainant along with 2x as promised under the Pre-EMI Scheme with Interest, B. Direct developer to pay loan outstanding amountAUTHORITY03/04/2024
ARVIND SANTHANAM PRASAD & ANOTHER vs M/S MANTRI DEVELOPERS PRIVATE LIMITEDA.Refund entire sale consideration, PRE-EMIs paid by Complainant along with 2x as promised under the Pre-EMI Scheme with Interest, B. Direct developer to pay loan outstanding amountAUTHORITY03/04/2024
GOURAV GUPTA & ANOTHER vs M/S MANTRI DEVELOPERS PRIVATE LIMITEDA.Refund entire sale consideration, PRE-EMIs paid by Complainant along with 2x as promised under the Pre-EMI Scheme with Interest, B. Direct developer to pay loan outstanding amount.AUTHORITY03/04/2024
SHUBHRA MISHRA & ANOTHER vs M/S MANTRI DEVELOPERS PRIVATE LIMITEDA.Refund entire sale consideration, PRE-EMIs paid by Complainant along with 2x as promised under the Pre-EMI Scheme with Interest, B. Direct developer to pay loan outstanding amount.AUTHORITY03/04/2024
SUMANT SUBHASHCHANDRA NAIKKHANVTE & ANOTHER vs M/S MANTRI DEVELOPERS PRIVATE LIMITEDA.Refund entire sale consideration, PRE-EMIs paid by Complainant along with 2x as promised under the Pre-EMI Scheme with Interest, B. Direct developer to pay loan outstanding amount.AUTHORITY03/04/2024
RAMANAN M vs M/S MANTRI DEVELOPERS PRIVATE LIMITEDA.Refund entire sale consideration, PRE-EMIs paid by Complainant along with 2x as promised under the Pre-EMI Scheme with Interest, B. Direct developer to pay loan outstanding amount.AUTHORITY03/04/2024
Dhruv Jhamb vs Mantri Developers Private LimitedAs prayed in the Facts of ComplaintAUTHORITY02/11/2022

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (138 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190211/0002111
11-02-2019
REFUND OF DOWN PAYMENT WITH 100% ASSURED RETURN UNDER BUYBACK, CLOSURE OF HOME LOAN WITH PNBHFL, PAYMENT OF INTEREST, REFUND OF EMIs PAID TO PNBHFL, COMPENSATIONMantri Webcity3A (another project by this promoter)DISPOSED AO
CMP/190222/0002125
22-02-2019
Completion and Possession not delivered in Mantri Webcity Projct by Mantri Developers Pvt LtdMantri Webcity3A (another project by this promoter)DISPOSED AO
CMP/190217/0002170
17-02-2019
Project delayed, pushed to acquire a higher cost apartment and further delay on the sameMantri Webcity3A (another project by this promoter)DISPOSED AO
CMP/190305/0002188
05-03-2019
REFUND OF DOWN PAYMENT WITH 100% ASSURED RETURN UNDER BUYBACK, CLOSURE OF HOME LOAN WITH PNBHFL, PAYMENT OF INTEREST, REFUND OF EMIs PAID TO PNBHFL, COMPENSATIONMantri Webcity2A (another project by this promoter)DISPOSED AO
CMP/190220/0002206
20-02-2019
Possession dates are registered wrongly with RERA for MANTRI WEBCITY 2AMantri Webcity2A (another project by this promoter)DISPOSED AO
CMP/190624/0002272
24-06-2019
Non Delivery of Apartment, Non payment of Pre-EMI, Delayed Compensation, Interest Refund, Damages for Mental Agony, Mental Torture and Unfair Trade PracticeMantri Webcity3B (another project by this promoter)DISPOSED AO
CMP/190225/0002286
25-02-2019
COMPLAINT UNDER SECTION 31 OF RERA 2016Mantri Webcity3C (another project by this promoter)DISPOSED AO
CMP/190319/0002378
19-03-2019
Buy Back closure 3 Years contract breached for indefinite period, Huge debt on Buyer for Pre-EMi and Home LoanMantri Webcity2BDISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectRSP-NARSP House, 30 Museum Road
ContractorM/S Simplex-NASC Road, Anand Rao circle
Structural engineerNAGESH CONSULTANTS---

Builder track record

RERA filing

Mantri has 8 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Mantri Developers”). 8 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹44.3 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Bank of Baroda Altamount Branch, Mumbai (IFSC BARB0ALTAMO, a/c …1041). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
MG Road / city centre5 km
Bellandur–Marathahalli belt10 km
Electronic City12 km
Outer Ring Road / Manyata12 km
Whitefield IT hub17 km
Kempegowda Int'l Airport32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Mantri Developers. View Mantri Developers's full track record →
Mantri Developers has 7 projects registered in Bangalore.

Other projects by this builder in Bangalore

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.