Bangalore/Project record

K-RERA · the public record

Oceanus Tranquil

Bengaluru East · Oceanus Dwellings (P)

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

28 Jun 2019declared completionK-RERA registration · read 20 Sep 2026
305registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 Jun 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

3.8registered acres

81.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/171208/000997

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion28 June 2019
Land area15,176 sq m (3.8 acres)
Homes registered305
Tower/wing entries4

In context

Density81.3 homes per acre
Density in context59th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units305Total inventory registered with K-RERA.
Registered land area15,176 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.49Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries4Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)305Separate filed counts; these categories may overlap and are not added together.
Open-parking field9Separate filed counts; these categories may overlap and are not added together.
Garage field368Separate filed counts; these categories may overlap and are not added together.
Project start date31-01-2014

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower A147676-
Tower B147777-
Tower C147676-
Tower D147676-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 305 official flat/unit rows, matching the 305 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2+STUDY16880.8-93.3 sqm47.8-60.7 sqm168
2BHK6080.8-90.7 sqm40.9-43.0 sqm60
3BHK5680.8-90.0 sqm61.4-62.2 sqm56
2 BHK2093.3 sqm41.4-43.0 sqm20
1BHK175.9 sqm27.6 sqm1

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower B7775.9-90.0 sqm27.6-62.1 sqm77
Tower A7693.3 sqm41.4-49.7 sqm76
Tower C7690.7 sqm41.3-52.6 sqm76
Tower D7680.8 sqm40.9-62.2 sqm76
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
101Tower A12+STUDY93.3 sqm49.7 sqm1
102Tower A12+STUDY93.3 sqm49.7 sqm1
103Tower A12+STUDY93.3 sqm47.9 sqm1
104Tower A12+STUDY93.3 sqm49.7 sqm1
105Tower A12 BHK93.3 sqm43.0 sqm1
106Tower A12 BHK93.3 sqm41.4 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 13 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 28 Jun 2019, extended (Section 6 Extension) to 28 Mar 2021 — both dates have passed with no OC on file. The extension on file was granted on 17 Jan 2020 (K-RERA extension no. EX/PRM/KA/RERA/1251/446/PR/200117/000997) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (3 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
AJAY SINGHA vs OCCANUS TRANQUILPraying for help to cancel this booking and help me to get my amount paid to builder and also return the loan amount given by bank to builder with interest and compensation.AUTHORITY28/10/2024
PREETHAM SHETTY vs OCEANUS DWELLINGS (P) LTDRefund at the earliest with 12% interest as agreed by the builder.AUTHORITY24/01/2023
Sindhu S Chandran vs OCEANUS DWELLINGS (P) LTDIntervention to get due compensation or acceptable change of allocated flat for the deviation from what was advertised and purchasedAUTHORITY20/07/2023

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (8 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190413/0002643
13-04-2019
Promoter demanding return of RERA penaltyOceanus Vista II T7 (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/190414/0002650
14-04-2019
Compensation for delayed project completionOceanus Vista II T7 (another project by this promoter)DISPOSED AO
CMP/190418/0002686
18-04-2019
Regarding RERA penalty clause for on-going projectsOceanus Vista II T7 (another project by this promoter)DISPOSED AUTHORITY
CMP/190422/0002697
22-04-2019
RERA PENALTYOceanus Vista II T7 (another project by this promoter)DISPOSED AO
CMP/190613/0003296
13-06-2019
REFUND THE PAID AMOUNT ALONG WITH INTERESTOceanus TranquilDISPOSED AO
CMP/190923/0004272
23-09-2019
Need to get Total Refund with Compensation due to delay in delivery of the projectOceanus Classic (another project by this promoter)DISPOSED AO
CMP/200823/0006122
23-08-2020
Refund due to Delay in CompletionOceanus TranquilDISPOSED AUTHORITY BENCH4
CMP/201011/0006820
11-10-2020
Open private terrace added below flatOceanus TranquilDISPOSED AUTHORITY BENCH6

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Builder track record

RERA filing

Oceanus Dwellings has 5 other K-RERA-registered projects in our records (average reported construction progress 87%). 2 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹21.5 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC BTM LAYOUT (IFSC HDFC0000885, a/c …5691). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata8 km
Whitefield IT hub10 km
MG Road / city centre11 km
Bellandur–Marathahalli belt11 km
Kempegowda Int'l Airport18 km
Electronic City22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Oceanus Dwellings. View Oceanus Dwellings's full track record →
Oceanus Dwellings has 6 projects registered in Bangalore, 2 completed.
7 complaints on the K-RERA register against Oceanus Dwellings in Bangalore.

Other projects by this builder in Bangalore

Oceanus Classic
Filing overdue · 99% built · 45% sold
Oceanus Vista II
Filing overdue · 100% built · 38% sold
Oceanus White Meadows
Filing overdue · 62% built · 66% sold

Other RERA-registered projects in Krishnarajapuram

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Oceanus Tranquil?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026