RERA Property Intelligence Report · Preview

PARAMOUNT BOULEVARD-2

PARAMOUNT CONSTRUCTION VENTURES · · K-RERA PRM/KA/RERA/1268/378/PR/111124/007216

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
7
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

102
Registered units
₹34.5 Cr
Est. construction cost
Units profiled
54
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units102Total inventory registered with K-RERA.
Official carpet area12,715 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area18,071 sqmUseful scale context when comparing density and project cost.
Registered land area7,175 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.36Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings1Official tower/wing count in the K-RERA detail page.
Parking disclosed160 total (149 covered, 11 open) — 1.57 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Approved plan numberHTG-LBPAS-00312/24-25/BPUse this to match the sanctioned drawing set shown by the builder.
Plan approval date13-06-2024
Project start date01-06-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 & 3 BHK102100%12,715 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
PARAMOUNT BOULEVARD-21310216044.9 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 102 official flat/unit rows, matching the 102 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK54100.7-168.5 sqm54.9-92.9 sqm54
2 BHK48100.7-130.6 sqm54.9-73.5 sqm48

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
PARAMOUNT BOULEVARD-2102100.7-168.5 sqm54.9-92.9 sqm102
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
G-1PARAMOUNT BOULEVARD-203 BHK124.2 sqm78.9 sqm1
G-2PARAMOUNT BOULEVARD-203 BHK103.2 sqm55.1 sqm1
G-3PARAMOUNT BOULEVARD-203 BHK168.5 sqm92.9 sqm1
G-4PARAMOUNT BOULEVARD-202 BHK100.7 sqm54.9 sqm1
G-5PARAMOUNT BOULEVARD-202 BHK100.7 sqm54.9 sqm1
101PARAMOUNT BOULEVARD-213 BHK124.2 sqm78.9 sqm1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~1,342 sqft — large-format homes (3BHK-and-up territory), not compact stock. This is a boutique, low-density project — 102 homes across 1 tower. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 160 parking spaces for 102 homes (~1.6 per home) — comfortable headroom over the 1-per-home many projects offer.
Your land share (UDS)Undivided land share averages ~70 sqm per home; across all 102 homes that is ~100% of the plot — a healthy sign: buyers collectively hold close to all the land. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

15 of 47 compliance document slots are filed as Not Applicable; the remaining 32 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

5 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved20-06-2024Water NOC 1.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved12-03-2023PollutionNOC.pdf
KPTCL- BESCOMApproved19-06-2024KEB NOCBoulevard2.pdf
Fire and SafetyApproved14-12-2023FireNOC.pdf
Airport Authority of IndiaApproved26-07-2023AirportNOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantSATISHA R & ASSOCIATES2258392011Mysore, Karnataka - 570016
EngineerGOPINATH RCA/2011/530472011Mysore, Karnataka - 560033
ArchitectGOPINATH RCA/2011/530472011Mysore, Karnataka - 560033
ContractorPARAMOUNT CONSTRUCTION COMPANY-2014Mysore, Karnataka - 570002

Builder track record

RERA filing

Paramount Construction has 7 other K-RERA-registered projects in our records (average reported construction progress 79%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹13.46 Cr collected from buyers, ₹13.46 Cr withdrawn from the project's escrow account.

Construction progress47% → 55% (+8 pts)
Units sold/booked as registered39/102 (38%)
Buyer collections in available QPRs₹18.86 Cr
Escrow withdrawals in available QPRs₹18.86 Cr (1.00x collections)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹33.8 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

Location & Connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
MG Road / city centre3 km
Outer Ring Road / Manyata10 km
Bellandur–Marathahalli belt12 km
Electronic City16 km
Whitefield IT hub19 km
Kempegowda Int'l Airport30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Paramount Construction. View Paramount Construction's full track record →
Paramount Construction has 7 projects registered in Bangalore, 1 completed.

Other projects by this builder in Bangalore

Paramount Boulevard-1
Filing overdue · 99% built · 48% sold
Paramount Oasis
Filing overdue · 88% built · 58% sold
Paramount Rhapsody
Filing overdue · 50% built · 62% sold

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.