Paramount Construction

Paramount Construction has 7 RERA-registered projects: 4 projects under construction, Bengaluru averaging 77% construction. All figures are the developer's own regulator filings.

Good record
Delivery signal
4
Under construction
2
Completed / delivered
52%
Bengaluru inventory booked

Under construction

Under construction — 4 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
PARAMOUNT BOULEVARD-1Bengaluru99%
PARAMOUNT OASIS Bengaluru95%
PARAMOUNT BOULEVARD-2Bengaluru63%
Paramount RhapsodyBengaluru50%
Considering a specific Paramount Construction project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Delivered projects (2)click to expand
ProjectCityStatus
PARAMOUNT GRANDEURBengaluruOC issued
PARAMOUNT SIDDHARTHABengaluruOC issued
Registered, no progress filed yet (1)click to expand
ProjectCity
PARAMOUNT ASPIREBengaluru

Figures are Paramount Construction's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.