Peninsula Pinewoods Phase - 2
Anekal · Peninsula Infra Developments
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Oct 2018
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 20 Sep 2026
Inventory & scale
What this registration contains.
Filed categories, unchanged · K-RERA registration · read 20 Sep 2026
The whole registration
3.6registered acres
The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1251/308/PR/171229/001796
This project, on the record
The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.
On the register
Values as crawled from the official K-RERA record; context percentiles name their comparison population.
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Registered land area | 14,467 sqm | The land area attached to this K-RERA registration. |
| Open-parking field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Garage field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Project start date | 31-10-2015 |
Official inventory & towers
RERA filingK-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.
Registered inventory mix
| Type | Units | Share | Official carpet area |
|---|---|---|---|
| No | 42 | 100% | 0 sqm |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingNo litigation declared on this project's K-RERA filing.
All 17 standard compliance document slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
⚠ Registration validity has lapsed: originally due 30 Oct 2018, extended (Section 6 Extension) to 30 Oct 2019 — both dates have passed with no OC on file. The extension on file was granted on 23 Jun 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/308/PR/220623/001796) — it has been used, its deadline has also passed, and no further extension is recorded.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
K-RERA complaint orders (2 complaints against a project of this name on K-RERA's orders register)
| Parties | Relief sought | Disposal | Order date |
|---|---|---|---|
| Shivakumara Krishna Avadhani vs Peninsula Infra Developers Pvt Ltd. | Request builder to buy back the plot with full refund, including applicable interest and compensation for delays, inconvenience, and mental stress caused. | AUTHORITY | 19/06/2026 |
| AJAY KUMAR RAUTARY vs Peninsula Infra Developements Pvt Ltd. | Respondent must complete all electrical, water, and sewage infrastructure in 90 days, pay for three-year delay and distress, and incur a penalty for missing statutory approvals. | AUTHORITY | 08/06/2026 |
⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.
Complaints on this project's K-RERA page (3 complaints listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/190813/0003869 13-08-2019 | Refund of Interest on Principal | Peninsula Solitaire (another project by this promoter) | DISPOSED AO |
| CMP/200827/0006450 27-08-2020 | Application for enforcement of AO Order dated 03rd January 2020 in Complaint No. CMP/190813/0003869 | Peninsula Solitaire (another project by this promoter) | DISPOSED AO |
| CMP/210630/0008071 30-06-2021 | Villa Registration | Peninsula Solitaire (another project by this promoter) | POSTED FOR ORDERS AUTHORITY BENCH4 |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
Builder track record
RERA filingPeninsula Infra has 6 other K-RERA-registered projects in our records. 6 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.
Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.
Financials & Construction Progress
Financial disclosures
RERA filing⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.
RERA 70% project account is on file: VIJAYA BANK BTM Layout (IFSC VIJB0001406, a/c …0443). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Construction photo filings
RERA filingK-RERA has 1 project-photo upload.
These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.
Location & Connectivity
The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Electronic City | 16 km |
| Bellandur–Marathahalli belt | 25 km |
| Whitefield IT hub | 30 km |
| MG Road / city centre | 31 km |
| Outer Ring Road / Manyata | 38 km |
| Kempegowda Int'l Airport | 54 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.