Pride Sunrise Phase-II

Anekal · Expert Investments

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2025declared completionK-RERA registration · read 20 Sep 2026
224registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

11
4
4
16
8
8
15
8
5
8
12
16
3
12
2
4
6
40
13
12
7
24
14
24
10
16
1
12
9
20

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.6registered acres

87.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/221122/005493

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 March 2025
Land area10,389 sq m (2.6 acres)
Homes registered224
Tower/wing entries5
Unit mix4 × 11, 16 × 4, 8 × 8, 8 × 15, 8 × 5, 16 × 12, 12 × 3, 4 × 2, 40 × 6, 12 × 13, 24 × 7, 24 × 14, 16 × 10, 12 × 1, 20 × 9

In context

Density87.3 homes per acre
Density in context66th percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units224Total inventory registered with K-RERA.
Official carpet area10,677 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area18,902 sqmUseful scale context when comparing density and project cost.
Registered land area10,389 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.38Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries5Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)178Separate filed counts; these categories may overlap and are not added together.
Covered-parking field153Separate filed counts; these categories may overlap and are not added together.
Open-parking field43Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberAPA/CC/149/2020-21Use this to match the sanctioned drawing set shown by the builder.
Plan approval date03-08-2022
Project start date15-01-2021

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
1142%55 sqm
4167%38 sqm
884%57 sqm
1584%54 sqm
584%55 sqm
12167%53 sqm
3125%53 sqm
242%53 sqm
64018%36 sqm
13125%39 sqm
72411%57 sqm
142411%36 sqm
10167%58 sqm
1125%55 sqm
9209%56 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Block-14805214.95 m
Block-24363614.95 m
Block-34363614.95 m
Block-44403014.95 m
Block-54322414.95 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 224 official flat/unit rows, matching the 224 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK13253.1-58.4 sqm45.0-51.6 sqm132
1 BHK9235.2-39.0 sqm31.3-33.8 sqm46 (46 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Block-18035.2-55.5 sqm31.3-47.9 sqm52 (28 with 0)
Block-44035.5-55.5 sqm31.5-47.7 sqm30 (10 with 0)
Block-23655.3-57.4 sqm49.0-50.5 sqm36
Block-33654.8-58.4 sqm46.7-51.6 sqm36
Block-53235.3-55.5 sqm31.5-47.7 sqm24 (8 with 0)
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-001Block-112 BHK55.5 sqm47.9 sqm1
A-002Block-112 BHK53.2 sqm45.6 sqm1
A-003Block-112 BHK53.4 sqm45.2 sqm1
A-004Block-111 BHK37.5 sqm32.7 sqm0
A-005Block-111 BHK37.5 sqm32.7 sqm1
A-006Block-111 BHK37.5 sqm32.7 sqm0

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 1 of 28 compliance document slots are filed as under process / not yet usable: Certificate from Chartered Account.

4 additional compliance slots are filed as Not Applicable.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Mar 2025 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantM/s. S. Janardhan & Associates, Mr. Vijay Bhatia005310S1991Bengaluru Urban, Karnataka - 560001
EngineerBELLAD DINESH KUMARBCCL/BL-3.6/SE-0218/21-222009Bengaluru Urban, Karnataka - 560080
ArchitectV.NARASIMHANCA/86/100341969Bengaluru Urban, Karnataka - 560025
ContractorSiddhivinayak Construction-2020Pune, Maharashtra - 413102

Builder track record

RERA filing

Expert Investments has 2 other K-RERA-registered projects in our records. 2 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹18.7 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Axis Bank Malleshwaram IFSC Code : UTIB0000227 Pin Code : 560003. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Electronic City9 km
Bellandur–Marathahalli belt19 km
MG Road / city centre21 km
Whitefield IT hub26 km
Outer Ring Road / Manyata29 km
Kempegowda Int'l Airport47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Expert Investments.
Expert Investments has 3 projects registered in Bangalore.
1 complaints on the K-RERA register against Expert Investments in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Electronic City

Major developers building in Electronic City

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.