RERA Property Intelligence Report · Preview

Renaissance Nature Walk Phase III (Building 04,Building 09 and Building 10)

RENAISSANCE HOLDINGS AND DEVELOPERS · Bengaluru East · K-RERA PRM/KA/RERA/1251/446/PR/171014/000162

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
6
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

61
Registered units
₹59.9 Cr
Est. construction cost
Units profiled
26
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units61Total inventory registered with K-RERA.
Official carpet area16,408 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area11,347 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI0.89Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings3Official tower/wing count in the K-RERA detail page.
Parking disclosed127 total (0 open) — 2.08 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date03-12-2016

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Row House61100%16,408 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Building 421022-
Building 922958-
Building 1022247-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 61 official flat/unit rows, matching the 61 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
4BHK61246.1-341.2 sqm167.4-223.3 sqm127

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Building 929248.9-275.6 sqm178.4-195.1 sqm58
Building 1022247.8-341.2 sqm178.4-223.3 sqm47
Building 410246.1-336.3 sqm167.4-223.3 sqm22
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
21Building 404BHK275.6 sqm195.1 sqm2
22Building 404BHK275.2 sqm195.1 sqm2
23Building 404BHK275.6 sqm195.1 sqm2
24Building 404BHK275.2 sqm195.1 sqm2
25Building 404BHK276.2 sqm195.1 sqm2
26Building 404BHK274.9 sqm195.1 sqm2

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~2,824 sqft — large, premium-format homes (4BHK/penthouse territory), not compact stock. This is a mid-scale project — 61 homes across 3 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 127 parking spaces for 61 homes (~2.1 per home) — comfortable headroom over the 1-per-home many projects offer.
Your land share (UDS)Undivided land share averages ~186 sqm per home; across all 61 homes that is ~100% of the plot — a healthy sign: buyers collectively hold close to all the land. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 22 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Jul 2020 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (3 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/210922/0008365
22-09-2021
Mismatch in land /boundary - not in accordance with Revenue records and conversion order . Deviation from the sanctioned plan -selling of 5mtr setback land against the clause 8 of snaction planRenaissance Nature Walk Phase III (Building 04,Building 09 and Building 10)UNDER ENQUIRY AUTHORITY FULLBENCH
CMP/210922/0008366
22-09-2021
Builder violating the Sanction Plan Setback AreasRenaissance Nature Walk Phase III (Building 04,Building 09 and Building 10)UNDER ENQUIRY AUTHORITY FULLBENCH
CMP/210922/0008367
22-09-2021
BUILDER VIOLATION OF SANCTION PLAN And ILLEGALLY SELLING SETBACK LANDRenaissance Nature Walk Phase III (Building 04,Building 09 and Building 10)UNDER ENQUIRY AUTHORITY FULLBENCH

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectRenaissance Holdings & Developers Private Limited-1994No 50 Landmark 17th Cross, 8th Main malleshwaram
ContractorM/s SH Constructions-2010K R Puram, Bangalore
Structural engineerVision Structural Design Aid---

Builder track record

RERA filing

Renaissance Holdings has 6 other K-RERA-registered projects in our records (average reported construction progress 80%). 5 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹98.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: ICICI Bank ICICI BANK LIMITED , MALLESWARAM BRANCH (IFSC ICIC0000078, a/c …1136). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 3 project-photo uploads.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata10 km
Whitefield IT hub10 km
Bellandur–Marathahalli belt13 km
MG Road / city centre14 km
Kempegowda Int'l Airport16 km
Electronic City24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Renaissance Holdings. View Renaissance Holdings's full track record →
Renaissance Holdings has 7 projects registered in Bangalore.

Other projects by this builder in Bangalore

Renaissance Srichakra
Filing overdue · 80% built · 62% sold
Renaissance Marigold Meadows
No filings
Renaissance Shanks Sunnyside
No filings

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Renaissance Nature Walk Phase III?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 27 Jul 2026