Bangalore/Project record

K-RERA · the public record

Renaissance Srichakra

Bengaluru North · Renaissance Holdings and Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ1 2026 filing
3units not bookedof 8 · Q1 2026 filing
11 Aug 2027declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

11 Aug 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Flats
8

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

0.2registered acres

34.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/309/PR/110325/007570

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion11 August 2027
Land area945 sq m (0.2 acres)
Homes registered8
Tower/wing entries1
Unit mix8 × Flats

In context

Density34.3 homes per acre
Density in context15th percentile of 525 Bengaluru North projects (median 75.4)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units8Total inventory registered with K-RERA.
Official carpet area1,480 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area2,088 sqmUseful scale context when comparing density and project cost.
Registered land area945 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.72Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)19Separate filed counts; these categories may overlap and are not added together.
Covered-parking field19Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberPRJ/13032/23-24Use this to match the sanctioned drawing set shown by the builder.
Plan approval date18-03-2024
Project start date12-08-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Flats8100%1,480 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Srichakra581914.95 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 8 official flat/unit rows, matching the 8 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
4 BHK8153.1-156.6 sqm116.7-119.8 sqm16

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Srichakra8153.1-156.6 sqm116.7-119.8 sqm16
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
001Srichakra14 BHK153.1 sqm116.7 sqm2
002Srichakra14 BHK156.6 sqm119.8 sqm2
101Srichakra24 BHK153.1 sqm116.7 sqm2
102Srichakra24 BHK156.6 sqm119.8 sqm2
201Srichakra34 BHK153.1 sqm116.7 sqm2
202Srichakra34 BHK156.3 sqm119.8 sqm2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

23 of 47 compliance document slots are filed as Not Applicable; the remaining 24 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (3 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/210922/0008365
22-09-2021
Mismatch in land /boundary - not in accordance with Revenue records and conversion order . Deviation from the sanctioned plan -selling of 5mtr setback land against the clause 8 of snaction planRenaissance Nature Walk Phase III (Building 04,Building 09 and Building 10) (another project by this promoter)UNDER ENQUIRY AUTHORITY FULLBENCH
CMP/210922/0008366
22-09-2021
Builder violating the Sanction Plan Setback AreasRenaissance Nature Walk Phase III (Building 04,Building 09 and Building 10) (another project by this promoter)UNDER ENQUIRY AUTHORITY FULLBENCH
CMP/210922/0008367
22-09-2021
BUILDER VIOLATION OF SANCTION PLAN And ILLEGALLY SELLING SETBACK LANDRenaissance Nature Walk Phase III (Building 04,Building 09 and Building 10) (another project by this promoter)UNDER ENQUIRY AUTHORITY FULLBENCH

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 5 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantSrikakolapu Varada Rajesh2287031987Bengaluru Urban, Karnataka - 560003
EngineerAnand GBCC/BL-3.6/E- 4435/2019-202006Bengaluru Urban, Karnataka - 560079
EngineerNeminath ParigondBCCL/BL-3.6/SE-0117/23-242003Bengaluru Urban, Karnataka - 560019
ArchitectKaavya RCA/2024/1689992023Bengaluru Urban, Karnataka - 560062
ContractorS M Constructions-2015Bengaluru Urban, Karnataka - 560003

Builder track record

RERA filing

Renaissance Holdings has 6 other K-RERA-registered projects in our records. 6 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.60 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress70% → 100% (+30 pts)
Units sold/booked as registered5/8 (62%)
Buyer collections in available QPRs₹17.82 Cr
  • Construction progress moved from 70% to 100% across the filed QPR window.
  • The builder has drawn 0.00x of buyer collections from escrow (about 0% of the ₹18 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹115.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: ICICI Bank Malleswaram IFSC Code : ICIC0001670 Pin Code : 560055. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
MG Road / city centre6 km
Outer Ring Road / Manyata7 km
Bellandur–Marathahalli belt16 km
Whitefield IT hub20 km
Electronic City21 km
Kempegowda Int'l Airport26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Renaissance Holdings. View Renaissance Holdings's full track record →
Renaissance Holdings has 7 projects registered in Bangalore, 1 completed.
3 complaints on the K-RERA register against Renaissance Holdings in Bangalore.

Other projects by this builder in Bangalore

Renaissance Marigold Meadows
No filings
Renaissance Nature Walk Phase III
No filings
Renaissance Shanks Sunnyside
No filings

Other RERA-registered projects in Malleshwaram

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Renaissance Srichakra?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026