REVIVA BY SSI

Anekal · SRI SAI INFRA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

44%construction reportedQ1 2026 filing
171units not bookedof 234 · Q1 2026 filing
31 Dec 2028declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK EAST B BLOCK TYPICAL
2
3 BHK EAST B BLOCK TYPICAL
2
2 BHK EAST A BLOCK TYPICAL
28
3 BHK WEST B BLOCK GF & FIRST FLOOR
2
3 BHK EAST B BLOCK TYPICAL
35
3 BHK EAST B BLOCK TYPICAL
7
3 BHK EAST B BLOCK GF & FIRST FLOOR
2
3 BHK EAST B BLOCK GF & FIRST FLOOR
10
3 BHK EAST B BLOCK TYPICAL
7
2 BHK WEST B BLOCK TYPICAL
28
2 BHK EAST A BLOCK GF & 1ST FLOOR
8
3 BHK NORTH A BLOCK GF & 1ST FLOOR
2
3 BHK EAST A BLOCK TYPICAL
14
3 BHK NORTH A BLOCK TYPICAL
7
3 BHK WEST B BLOCK GF & FIRST FLOOR
2
3 BHK WEST B BLOCK TYPICAL
7
3 BHK WEST B BLOCK TYPICAL
7
3 BHK EAST B BLOCK TYPICAL
7
2 BHK WEST B BLOCK GF & FIRST FLOOR
8
3 BHK WEST A BLOCK GF & 1ST FLOOR
10
3 BHK EAST A BLOCK GF & 1ST FLOOR
4
3 BHK WEST A BLOCK TYPICAL
35

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

3.0registered acres

78.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/130525/007735

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2028
Land area12,037 sq m (3.0 acres)
Homes registered234
Tower/wing entries2
Unit mix60 × 3 BHK EAST B BLOCK TYPICAL, 28 × 2 BHK EAST A BLOCK TYPICAL, 4 × 3 BHK WEST B BLOCK GF & FIRST FLOOR, 12 × 3 BHK EAST B BLOCK GF & FIRST FLOOR, 28 × 2 BHK

In context

Density78.7 homes per acre
Density in context54th percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units234Total inventory registered with K-RERA.
Official carpet area24,358 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area38,306 sqmUseful scale context when comparing density and project cost.
Registered land area12,037 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)258Separate filed counts; these categories may overlap and are not added together.
Covered-parking field258Separate filed counts; these categories may overlap and are not added together.
Open-parking field21Separate filed counts; these categories may overlap and are not added together.
Garage field1Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBMRDA/TP/564/2024-25Use this to match the sanctioned drawing set shown by the builder.
Plan approval date01-03-2025
Project start date04-03-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK EAST B BLOCK TYPICAL21%92 sqm
3 BHK EAST B BLOCK TYPICAL21%86 sqm
2 BHK EAST A BLOCK TYPICAL2812%66 sqm
3 BHK WEST B BLOCK GF & FIRST FLOOR21%92 sqm
3 BHK EAST B BLOCK TYPICAL3515%84 sqm
3 BHK EAST B BLOCK TYPICAL73%88 sqm
3 BHK EAST B BLOCK GF & FIRST FLOOR21%90 sqm
3 BHK EAST B BLOCK GF & FIRST FLOOR104%80 sqm
3 BHK EAST B BLOCK TYPICAL73%94 sqm
2 BHK WEST B BLOCK TYPICAL2812%67 sqm
2 BHK EAST A BLOCK GF & 1ST FLOOR83%66 sqm
3 BHK NORTH A BLOCK GF & 1ST FLOOR21%90 sqm
3 BHK EAST A BLOCK TYPICAL146%90 sqm
3 BHK NORTH A BLOCK TYPICAL73%91 sqm
3 BHK WEST B BLOCK GF & FIRST FLOOR21%90 sqm
3 BHK WEST B BLOCK TYPICAL73%93 sqm
3 BHK WEST B BLOCK TYPICAL73%92 sqm
3 BHK EAST B BLOCK TYPICAL73%92 sqm
2 BHK WEST B BLOCK GF & FIRST FLOOR83%67 sqm
3 BHK WEST A BLOCK GF & 1ST FLOOR104%80 sqm
3 BHK EAST A BLOCK GF & 1ST FLOOR42%38 sqm
3 BHK WEST A BLOCK TYPICAL3515%82 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
ALOHA810812028.02 m
BLISS812613828.02 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 234 official flat/unit rows, matching the 234 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK16280.5-93.7 sqm48.9-55.4 sqm162
2 BHK7266.4-67.0 sqm38.8-40.3 sqm72

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
BLISS12666.8-93.7 sqm39.2-55.0 sqm126
ALOHA10866.4-90.8 sqm38.8-55.4 sqm108
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
AG01ALOHA03 BHK80.5 sqm48.9 sqm1
AG02ALOHA03 BHK80.5 sqm48.9 sqm1
AG03ALOHA03 BHK80.5 sqm48.9 sqm1
AG04ALOHA03 BHK80.5 sqm48.9 sqm1
AG05ALOHA03 BHK80.5 sqm48.9 sqm1
AG06ALOHA03 BHK90.8 sqm53.5 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 31 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved20-05-2025NOCWater.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved13-11-2025CFE KSPCB Sri Sai Infra datedcompressed.pdf
KPTCL- BESCOMApproved28-10-2024BESCOM NOC BN .pdf
Fire and SafetyApproved20-09-2024FIRE NOC.pdf
Airport Authority of IndiaApproved12-06-2024AIRPORT.pdf
BSNL/Telecommunication DepartmentApproved06-11-2024BSNL NOC Sri sai Infra dated.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantI V S S RAJU2182822006Bengaluru Urban, Karnataka - 560037
EngineerN VAMSHI KRISHNA190/Strl Engineer/TP10/GHMC/232016Ranga Reddy, Telangana - 500074
ArchitectMAHEEDHAR MCA/2011/510462018Ranga Reddy, Telangana - 500081
ContractorKSR INFRA-2017Ranga Reddy, Telangana - 500081

Builder track record

RERA filing

Sri Sai has 18 other K-RERA-registered projects in our records (average reported construction progress 73%). 6 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹8.73 Cr collected from buyers, ₹8.73 Cr withdrawn from the project's escrow account.

Construction progress25% → 44% (+19 pts)
Units sold/booked as registered63/234 (27%)
Buyer collections in available QPRs₹26.58 Cr
Escrow withdrawals in available QPRs₹26.58 Cr (1.00x collections)
  • Construction progress moved from 25% to 44% across the filed QPR window.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹35.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC MARATHAHALLI IFSC Code : HDFC0001756 Pin Code : 560081. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Electronic City7 km
Bellandur–Marathahalli belt16 km
Whitefield IT hub20 km
MG Road / city centre22 km
Outer Ring Road / Manyata29 km
Kempegowda Int'l Airport45 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sri Sai.
Sri Sai has 19 projects registered in Bangalore, 4 completed.

Other projects by this builder in Bangalore

SRI SAI Layout
Filing overdue · 100% built
Ssvd Serenity
Filing overdue · 12% built · 0% sold
Sri Sai Garden
Filing overdue · 100% built
Sri Sai Krupa Meadows
Filing overdue · 100% built · 44% sold
Concorde Elements Of Earth
No filings

Other RERA-registered projects in Electronic City

Major developers building in Electronic City

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.