87%construction reportedQ4 2025 filing

The record · free to read

Registration read 04 Jul 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q4 2025

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 04 Jul 2026

Inventory & scale

What this registration contains.

6.1 mX9.14 M
68

Filed categories, unchanged · K-RERA registration · read 04 Jul 2026

The whole registration

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/303/PR/211024/007160

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Unit mix68 × 6.1 mX9.14 M

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Approved plan numberDod/1-2/2026-27Use this to match the sanctioned drawing set shown by the builder.
Plan approval date26-06-2026
Project start date27-05-2026

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
6.1 mX9.14 M68100%3,791 sqm

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

1 of 24 compliance document slots are filed as Not Applicable; the remaining 23 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (NOC from ESCOMs)
Water & sewage (BWSSB/KWSSB)✓ On file (NOC for Water)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB (If Applicable))
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC and environmental clearance are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

8 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved03-08-2024BhumiWater NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved06-01-2025Sattva Bhoomi Podar property CFEcompressed.pdf
KPTCL- BESCOMApproved04-06-2024Bhumi Bescom NOC.pdf

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantYash Jain Katariya C021233S2019Bengaluru Urban, Karnataka - 560020
EngineerRSPBCC/BBMP - 15-20102010Bengaluru Urban, Karnataka - 560063

Builder track record

RERA filing

Shirasa Construction has 2 other K-RERA-registered projects in our records (average reported construction progress 100%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹17.88 Cr collected from buyers, ₹7.87 Cr withdrawn from the project's escrow account.

Construction progress80% → 87% (+7 pts)
Buyer collections in available QPRs₹43.57 Cr
Escrow withdrawals in available QPRs₹25.83 Cr (0.59x collections)
  • Construction progress moved from 80% to 87% across the filed QPR window.
  • The builder has drawn 0.59x of buyer collections from escrow (about 59% of the ₹44 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

RERA 70% project account is on file: ICICI Bank HAL 2nd Stage Indiranagar Branch IFSC Code : ICIC0001668 Pin Code : 560038. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~32 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kempegowda Int'l Airport13 km
Outer Ring Road / Manyata32 km
Whitefield IT hub36 km
MG Road / city centre39 km
Bellandur–Marathahalli belt41 km
Electronic City51 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Shirasa Construction.
Shirasa Construction has 3 projects registered in Bangalore, 1 completed.

Other projects by this builder in Bangalore

Sattva Bhumi
On track · 100% built

Other RERA-registered projects in Devanahalli

Major developers building in Devanahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.