Bangalore/Project record

K-RERA · the public record

South Park phase 2

Bengaluru South · ESTEEM SOUTH PARKS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

99%construction reportedQ3 2025 filing
95units not bookedof 219 · Q3 2025 filing
31 Dec 2026declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q3 2025

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2BHK
90
2.5BHK 2T
129

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.1registered acres

106.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/090523/005912

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2026
Land area8,310 sq m (2.1 acres)
Homes registered219
Tower/wing entries2
Unit mix90 × 2BHK, 129 × 2.5BHK 2T

In context

Density106.7 homes per acre
Density in context85th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units219Total inventory registered with K-RERA.
Official carpet area11,948 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area28,927 sqmUseful scale context when comparing density and project cost.
Registered land area8,310 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)219Separate filed counts; these categories may overlap and are not added together.
Covered-parking field142Separate filed counts; these categories may overlap and are not added together.
Open-parking field103Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/Addl.Dir/JDsouth/0015/2022-23Use this to match the sanctioned drawing set shown by the builder.
Plan approval date23-11-2022
Project start date01-07-2021

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2BHK9041%4,310 sqm
2.5BHK 2T12959%7,639 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A14656544.9 m
B1415415445 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 219 official flat/unit rows, matching the 219 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2.5 BHK12958.9-59.8 sqm31.9-35.1 sqm129
2 BHK9044.8-50.6 sqm23.4-28.0 sqm90

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
B15446.9-59.2 sqm24.1-33.1 sqm154
A6544.8-59.8 sqm23.4-35.1 sqm65
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
101 AA12.5 BHK59.8 sqm32.5 sqm1
102 AA12.5 BHK59.5 sqm33.0 sqm1
103 AA12 BHK44.8 sqm23.4 sqm1
104 AA12.5 BHK59.6 sqm33.4 sqm1
105 AA12.5 BHK59.3 sqm35.1 sqm1
201 AA22.5 BHK59.8 sqm33.8 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

23 of 45 compliance document slots are filed as Not Applicable; the remaining 22 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved08-04-2022BWSSB NOC-04-08-2022.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved21-10-2022Shiva Enterprises- KSPCB Extension Letter.pdf
KSPCB- MOEF (Above 50 Acres)Approved17-03-2015Shiva Enterprises Enivroment NOC.pdf
KPTCL- BESCOMApproved28-06-2022BESCOM NOC - 28062022.pdf
Fire and SafetyApproved29-08-2022Revised FIRE NOC -29-08-2022.pdf
Airport Authority of IndiaApproved04-08-2022Esteem South Parks Airport NOC copy.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantSagar & Dhananjaya0140072012Bengaluru Urban, Karnataka - 560079
EngineerNadig ConsultingBCC/BL 3.6/E – 4059/14-152015Bengaluru Urban, Karnataka - 560001
ArchitectArchitects IncCA/94/179581992Bengaluru Urban, Karnataka - 560032
ContractorImperial Built tech private limited-2017Bengaluru Urban, Karnataka - 560070

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q3): ₹7.24 Cr collected from buyers, ₹7.24 Cr withdrawn from the project's escrow account.

Construction progress99% → 99% (+0 pts)
Units sold/booked as registered124/219 (57%)
Buyer collections in available QPRs₹7.24 Cr
Escrow withdrawals in available QPRs₹7.24 Cr (1.00x collections)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹26.5 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Punjab National Bank sadashivnagar IFSC Code : PNB001001 Pin Code : 560080. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Electronic City8 km
MG Road / city centre13 km
Bellandur–Marathahalli belt14 km
Outer Ring Road / Manyata21 km
Whitefield IT hub21 km
Kempegowda Int'l Airport40 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Esteem South.
Esteem South has 2 projects registered in Bangalore, 2 completed.

Other projects by this builder in Bangalore

South Park Phase 1
On track · 109% built · 72% sold

Other RERA-registered projects in J. P. Nagar

Major developers building in J. P. Nagar

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in South Park Phase 2?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026