Bangalore/Project record

K-RERA · the public record

SOWMYA SKYLA

Anekal · SOWMYA INFRA PROJECTS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

90%construction reportedQ1 2026 filing
57units not bookedof 68 · Q1 2026 filing
31 Dec 2026declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Flats of 3 BHK
35
Flats of 2 BHK
33

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

0.9registered acres

78.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/220324/006727

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2026
Land area3,515 sq m (0.9 acres)
Homes registered68
Tower/wing entries2
Unit mix35 × Flats of 3 BHK, 33 × Flats of 2 BHK

In context

Density78.3 homes per acre
Density in context53rd percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units68Total inventory registered with K-RERA.
Official carpet area5,688 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area8,011 sqmUseful scale context when comparing density and project cost.
Registered land area3,515 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.74Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)68Separate filed counts; these categories may overlap and are not added together.
Covered-parking field75Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan number33/75Use this to match the sanctioned drawing set shown by the builder.
Plan approval date14-08-2023
Project start date01-01-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Flats of 3 BHK3551%3,254 sqm
Flats of 2 BHK3349%2,434 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Sowmya Skyla A Block4363614.95 m
Sowmya Skyla B Block4323214.95 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 68 official flat/unit rows, matching the 68 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK3587.5-97.0 sqm50.2-61.7 sqm35
2 BHK3366.8-87.5 sqm39.5-55.8 sqm33

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Sowmya Skyla A Block3670.6-95.8 sqm41.4-58.3 sqm36
Sowmya Skyla B Block3266.8-97.0 sqm39.5-61.7 sqm32
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-001Sowmya Skyla A Block03 BHK89.6 sqm51.5 sqm1
A-002Sowmya Skyla A Block03 BHK94.5 sqm53.6 sqm1
A-003Sowmya Skyla A Block02 BHK74.8 sqm45.4 sqm1
A-004Sowmya Skyla A Block03 BHK90.0 sqm51.8 sqm1
A-005Sowmya Skyla A Block02 BHK72.6 sqm42.6 sqm1
A-006Sowmya Skyla A Block03 BHK93.1 sqm53.5 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

7 of 28 compliance document slots are filed as Not Applicable; the remaining 21 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC and environmental clearance are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

7 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved14-03-2023Water NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved01-07-2023KSPCB NOC.pdf
KPTCL- BESCOMApproved11-10-2023BESCOM NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantVENKATRAMANA P2284082017Bengaluru Urban, Karnataka - 560016
EngineerDr Mahadev Achar MF-12332262015Bengaluru Urban, Karnataka - 560056
ArchitectVinod Kumar KCA/2015/679822015Bengaluru Urban, Karnataka - 560094
ContractorSOWMYA INFRA PROJECTS-2021Bengaluru Urban, Karnataka - 562107

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress80% → 90% (+10 pts)
Units sold/booked as registered11/68 (16%)
Buyer collections in available QPRs₹0.86 Cr
Escrow withdrawals in available QPRs₹0.86 Cr (1.00x collections)
  • Construction progress moved from 80% to 90% across the filed QPR window.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹38.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC HOODI IFSC Code : HDFC0009441 Pin Code : 560048. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Electronic City4 km
Bellandur–Marathahalli belt12 km
Whitefield IT hub17 km
MG Road / city centre19 km
Outer Ring Road / Manyata25 km
Kempegowda Int'l Airport41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sowmya Infra.

Other RERA-registered projects in Electronic City

Major developers building in Electronic City

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.