A family entering the festive market is being pointed to the same comfort zone: homes between ₹50 lakh and ₹1.5 crore, with job security shaping how far buyers stretch, per Hindustan Times. That is the mood of the season. The harder question sits in the registered filings: does the home come in December 2027, November 2029, October 2030, March 2034 or December 2035?
Quietlist's read of the official K-RERA, MahaRERA, UP-RERA and HRERA filings points to a cross-city split. Pune gives the shortest possession dates in this set. Indirapuram and Panvel sit in the late-2029 band. Gurgaon moves the discussion to larger future supply. Bangalore's Fraser Town phases and Sewri in Mumbai ask the buyer to accept a much longer wait.
The filings used here give timelines and QPR progress. They do not give sale prices for this comparison. So the useful buyer question is plain: how long can the household wait?
The First Cut Is Calendar
A household trying to reduce rent overlap will read Pune first. Signature Business Centre in Bhugaon carries a December 2027 possession date, per its MahaRERA project filing. Prestige Business Hub in Moshi follows with June 2028. Signature Space Realty in Kirkatwadi carries December 2028. Prestige Platinum in Saswad reaches January 2030.
That makes Pune the cleanest place in this multi-city read for buyers who want the registered handover date to arrive before the decade turns too far. A shorter wait lowers the number of lease renewals, school decisions and rent months that must be planned before possession.
Late 2029 Is The Middle Lane
The late-2029 group is where the festive buyer should slow down and compare like with like.
In Indirapuram, Mayflower AT THE Prestige City and Mulberry AT THE Prestige City both carry November 2029 possession dates, per their UP-RERA project filings. A buyer comparing them is not choosing between delivery years. The useful questions move to layout, payment schedule, location inside the township and comfort with the builder's offering.
Panvel sits close to the same frame. Bhagwati Elysia III and Bhagwati Elysia IV in Panvel both carry December 2029 possession dates, per their MahaRERA project filings. Indirapuram and Panvel are different city markets, but they ask a similar planning question: can the family treat late 2029 as the real move-in horizon?
Possession Years Across The Cross-City Set
possession year
Source: K-RERA, MahaRERA, UP-RERA and HRERA project filings in the register read
Gurgaon Changes The Homework
Gurgaon is where the buyer sees registered supply at a larger project scale, then decides whether that scale is worth a longer wait.
Sobha Aranya Phase-1 in Sector 80 reported 527 registered units in its Q2 2026 QPR filing with HRERA, filed on 15 July 2026, with possession targeted for October 2030. Sobha Altus in Sector 106 reported 296 registered units in its Q2 2026 QPR filing with HRERA, also filed on 15 July 2026, with possession targeted for December 2031.
Scale changes the homework. In a nearer project, the main question may be whether the handover date fits the household's next move. In a larger future community, the buyer also has to read the phase, the promised common facilities and the timing of the surrounding development.
Bangalore Rewards Patience
Fraser Town brings a different trade-off. The address may be familiar, and the filings give the buyer a clear staged picture.
Sobha Crystal Meadows Phase 2 and Phase 3 each reported 59 units and 0% construction in their Q4 2025 QPR filings with K-RERA, filed on 13 April 2026. Phase 4 reported 42 units and 0% construction in the same filing cycle. Phase 5 reported 93 units and 0% construction, with possession targeted for December 2035.
June 2031, December 2032, December 2033 and December 2035 are four different household plans. The patient buyer may prefer a phased programme in a known locality. The impatient buyer should read the same filings and keep the search wider.
Mumbai Is Two Timelines
Mumbai cannot be treated as one answer in this read.
Sobha Inizio in Sewri is registered with MahaRERA for March 2034 possession. That is a long-date purchase. It may suit a buyer who wants Sewri and can plan around a later handover.
Panvel is a different decision. Bhagwati Elysia III and Bhagwati Elysia IV both carry December 2029 possession dates, per their MahaRERA project filings. In the register view, Panvel sits closer to Indirapuram than to Sewri. The same metro region gives two very different waiting periods.
The Register View
| City | Project | Builder | Locality | Reg number | Possession date | Filing evidence |
|---|---|---|---|---|---|---|
| Pune | Signature Business Centre | Signature Landmarks LLP | Bhugaon | P52100049606 | December 2027 | MahaRERA project filing |
| Pune | Prestige Business Hub | Prestige Associates | Moshi | PC1260002500606 | June 2028 | MahaRERA project filing |
| Pune | Signature Space Realty | Signature Space Realty | Kirkatwadi | PM1260002502757 | December 2028 | MahaRERA project filing |
| Noida | Mayflower AT THE Prestige City | Prestige | Indirapuram | UPRERAPRJ430385/07/2025 | November 2029 | UP-RERA project filing |
| Noida | Mulberry AT THE Prestige City | Prestige | Indirapuram | UPRERAPRJ470993/04/2025 | November 2029 | UP-RERA project filing |
| Mumbai | Bhagwati Elysia III | Bhagwati Signature LLP | Panvel | P52000056158 | December 2029 | MahaRERA project filing |
| Mumbai | Bhagwati Elysia IV | Bhagwati Signature LLP | Panvel | P52000056049 | December 2029 | MahaRERA project filing |
| Pune | Prestige Platinum | The Prestige Group | Saswad | PM1260002500447 | January 2030 | MahaRERA project filing |
| Gurgaon | Sobha Aranya Phase-1 | Sobha | Sector 80 | RERA-GRG-1565-2024 | October 2030 | HRERA Q2 2026 QPR filed 15 July 2026; 527 units |
| Bangalore | Sobha Crystal Meadows Phase 2 Wing 7 And 8 | Sobha | Fraser Town | KA-11721 | June 2031 | K-RERA Q4 2025 QPR filed 13 April 2026; 59 units; 0% construction |
| Gurgaon | Sobha Altus | Sobha | Sector 106 | RERA-GRG-1564-2024 | December 2031 | HRERA Q2 2026 QPR filed 15 July 2026; 296 units |
| Bangalore | Sobha Crystal Meadows Phase 3 Wing 9 To 15 | Sobha | Fraser Town | KA-11745 | December 2032 | K-RERA Q4 2025 QPR filed 13 April 2026; 59 units; 0% construction |
| Bangalore | Sobha Crystal Meadows Phase 4 Wing 23 To 28 | Sobha | Fraser Town | KA-11751 | December 2033 | K-RERA Q4 2025 QPR filed 13 April 2026; 42 units; 0% construction |
| Mumbai | Sobha Inizio | Sobha Limited | Sewri | PR1170002501523 | March 2034 | MahaRERA project filing |
| Bangalore | Sobha Crystal Meadows Phase 5 Wing 16 To 22 | Sobha | Fraser Town | KA-11758 | December 2035 | K-RERA Q4 2025 QPR filed 13 April 2026; 93 units; 0% construction |
What The Buyer Should Do
The festive discount is the opening line. The filing is the main document.
A buyer who needs a nearer handover should start with the Pune dates and then compare the project details. A buyer who can wait until late 2029 can compare Indirapuram and Panvel with a clearer head, because the possession year is similar. Gurgaon needs a wider read: when possession is promised, how the project scale fits the family's plan, and what the phase documents say. Bangalore's Fraser Town phases need patience, and that patience should be chosen early.
The ₹50 lakh-to-₹1.5 crore mood explains why buyers are careful this season. The register shows how to be careful. Begin with the month your life can actually absorb.