Mumbai/Project record

MahaRERA · the public record

AADHESHWAR PLAZA

Wakan Pali Road · SHAILESH VIJAY DHARIA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000020683

Delivery and registration

When is the project declared for completion?

AADHESHWAR PLAZA is registered with MahaRERA as P52000020683 and the promoter has declared completion for 31 Mar 2023.

31 Mar 2023

declared completion

42months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000020683
Registered on03 May 2019
Promoter-declared completion31 Mar 2023
Current statusCertificate Signed
Against todayabout 42 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AADHESHWAR PLAZA record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shailesh Vijay Dharia is the promoter of record on 33 projects registered with MahaRERA, 7 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

33projects

registered with MahaRERA

7flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AADHESHWAR PLAZA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
AADESHWAR PLAZA A WING1G+531 Dec 2021
AADESHWAR PLAZA B WING1G+531 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2023As due to Covid 19 there was unavailability of labour and material shortage was there hence project got delayed.

Location, Land & Connectivity

Located at Wakan Pali Road, Wakan Pali Road NH548A, Pali Tal-Sudhagad,Dist-Raigad, Haveli, Pune, 410205. Per the filed land record, the plot is bounded to the north by SURVEY NUMBER 166, to the south by SURVEY NUMBER 164, to the east by GAVTHAN PLOT and to the west by SURVEY NUMBER 156. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district29 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pali

Shubham Residency
possession by Oct 2026 · G D Jain Infra Projects
Annaprabha Complex
possession by Dec 2026 · Kishor Prabhakar Dandekar
City Of Music Phase III
possession by Dec 2026 · Nirvana Leisure Realty
City OF Music Phase IV
possession by Dec 2026 · Nirvana Leisure Realty
Joy Villa Phase-I
possession by Dec 2026 · Sadanand Laxmanrao Patil
Kenisha Resort Residences
possession by Dec 2026 · Kpin Real Estate Ventures

Other RERA-registered projects in Raigarh

Aadinath Heights
possession by Dec 2029 · Ess Gee Tradefin Private Limited
Aaditya Lakshmi Narayan
possession by Dec 2029 · Arvind Mahadev Sawlekar
Aaditya OM SAI Prasad
possession by Dec 2026 · Aaditya Infrastructures Private Limited
Aaditya Rudra
declared completion Dec 2023 · Rudra Realtors
AAI Residency
declared completion Jun 2026 · Gunwant Bhagawan Gowari
Aaiji Complex
possession by Dec 2028 · Om Sai Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026