Mumbai/Project record

MahaRERA · the public record

Aarambh Infracon

Vihighar · Aditi Ashish Sonar

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000027986

Delivery and registration

When is the project declared for completion?

Aarambh Infracon is registered with MahaRERA as P52000027986 and the promoter has declared completion for 30 Jun 2026.

30 Jun 2026

declared completion

3months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000027986
Registered on24 Jan 2021
Promoter-declared completion30 Jun 2026
Current statusCertificate Signed
Against todayabout 3 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Aarambh Infracon record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Aditi Ashish Sonar is the promoter of record on 86 projects registered with MahaRERA, 14 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

86projects

registered with MahaRERA

14flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Aarambh Infracon in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
A Wing1G+531 Dec 2025
B Wing1G+531 Dec 2025
C wing1G+531 Dec 2025
D Wing1G+531 Dec 2025
E wing1G+531 Dec 2025
F Wing1G+431 Dec 2025
G Wing1G+431 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Vihighar, Nere Matheran Road, Kalyan, Thane, 410206. Per the filed land record, the plot is bounded to the north by Gat No 143, to the south by Gat No 148, to the east by Border of Nere Village and to the west by Gat No 146. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Arihant Clan Aalishan Phase I
possession by Sep 2026 · Arihant Vatika Realty Private Limited
Balaji Heritage
possession by Sep 2026 · Buildfox Realty LLP
Delta Hills
possession by Sep 2026 · Shree Ganesh Enterprises
Delta Riviera
possession by Sep 2026 · Shreenathji Organisers Pvt. Ltd.
GAJ Oasis
possession by Sep 2026 · Shiv Builders AND Developers
Green View
possession by Sep 2026 · Siddhivinayak Developers

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Aarambh Residency
declared completion Jun 2023 · Gurudarshan Realtors
Aarambh Residency C1 D1
declared completion Nov 2020 · Shreeram Builders & Developers
Aarambh Residency G1 G2
declared completion Dec 2024 · Shreeram Builders & Developers
Aarambha Residency Ekadanta
declared completion Dec 2021 · Shreeram Builders & Developers
Aarohi Complex
declared completion Jul 2025 · M/S Today Shyam Developers
Aarsh Bhanudas
possession by Dec 2026 · Poonam Bhanudas Mokal

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026