Mumbai/Project record

MahaRERA · the public record

AAVAAS CLASSIC

Mumbai City · M. K. REALTORS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800001554

Delivery and registration

When is the project declared for completion?

AAVAAS CLASSIC is registered with MahaRERA as P51800001554 and the promoter has declared completion for 30 Mar 2022.

30 Mar 2022

declared completion

54months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800001554
Registered on28 Jul 2017
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 54 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AAVAAS CLASSIC record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AAVAAS CLASSIC in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
AAVAAS CLASSIC1G+20-
NICOLASWADI CHSL SRA1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2020The Project proposal is under Slum Rehabilitation Authority under Regulation 33(10) of DCR 1991 and recently due to Additional Eligibility of the Slum Dwellers in the Project, the
30 Sep 202030 Sep 2020To, Date: 23-Sep-2019 MAHARERA, Bandra East, Mumbai-400 051. Sub: Request for RERA Deadline Extension Registration No.P51800001554. Respected Sir, I, H
30 Sep 202030 Sep 2020Draft application for Rera Extension for Aavaas Classic - Nicolaswadi, Dahisar(west), Mumbai; Sub : SRA project at Nicolaswadi, Dahisar(west), Mumbai ...........Request to gran
30 Sep 202030 Sep 2021Respected Sir, Pranam For our building, Aavaas Classic, the construction activity has been completed and finishing is going on. Apart from this we are in the process of getting t

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400068. Per the filed land record, the plot is bounded to the north by CIS NO 685A, to the south by CTS NO 694, to the east by CTS NO 690 693 AND 694 and to the west by DAHISAR RIVER. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ14 km
Powai / Hiranandani business park16 km
Chhatrapati Shivaji Int'l Airport18 km
Bandra Kurla Complex (BKC)21 km
Lower Parel / Worli business district29 km
Nariman Point / Fort37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every M. K. Realtors project & its RERA track record →

Other RERA-registered projects in Dahisar East

Bhaveshwar Heights
possession by Sep 2026 · Shree Krishna Real Estate And Developers
Padma Apartment CO-Operative Housing Society Limited
possession by Sep 2026 · Haritara Construction Company Private Li
Jeandveekedarnath
possession by Dec 2026 · JE AND VEE Infrastructure
Shri Upendra Chsl
possession by Dec 2026 · Harshal Enterprises
Swayam Niketan
possession by Dec 2026 · Jainam Associates
A And O Eminente
Not filing quarterly progress reports · possession by Dec 2026 · Ashapura Housing Private Limited

Major developers building in Dahisar East

Other RERA-registered projects in Mumbai Suburban

Aayush Aurum
possession by Sep 2028 · Aayush Builders & Developers LLP
Aayush Ayaansh
declared completion Dec 2025 · Aayush Developers
Aayush Gokul
possession by Jun 2027 · Aayush Developers
Aayush Poornima
declared completion Dec 2020 · Aayush Developers
Abhilash
declared completion Mar 2022 · Sanjona Builders
Abhilash Phase II
possession by Mar 2027 · Sanjona Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026