MahaRERA Property Intelligence · Mumbai Suburban

Aayush Aura

P51800000622 · promoter Aayush Arrtha Realtors

Certificate SignedDue 31 Dec 2019

Delivery & Registration

MahaRERA registrationP51800000622
Registered on18 Jul 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 79 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Aayush Arrtha Realtors is the promoter of record on 19 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Aayush Aura1G+731 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 201931 Dec 2019We would like to bring up some facts about the project, which have caused unavoidable delay in the project. As per IOD plan dated 23rd March 2016, the project consist of Stilt plus

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400074. Per the filed land record, the plot is bounded to the north by Plot bearing CTS No 360, to the south by Plot bearing CTS No 364, to the east by Plot bearing CTS No 349 348 347 346 and to the west by 30 Feet Wide Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport6 km
Lower Parel / Worli business district8 km
Powai / Hiranandani business park9 km
Andheri MIDC / SEEPZ10 km
Nariman Point / Fort15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chembur

Satwaratna Co Op Hsg Society Ltd
possession by Sep 2026 · Kishrajdevelopers
Bhagwan Residency
possession by Oct 2026 · V3 Partners
Safal Ganga Smruti
possession by Nov 2026 · Varun Homes PVT LTD
Jade Residences
possession by Dec 2026 · JSR Realty
SAI Orion
possession by Dec 2026 · Vineet Buildcon Private Limited
D J Nest
possession by Mar 2027 · Dhiraj Narayandas Jadhwani

Other RERA-registered projects in Mumbai Suburban

Aayush Aurum
possession by Sep 2028 · Aayush Builders & Developers LLP
Aayush Ayaansh
declared completion Dec 2025 · Aayush Developers
Aayush Gokul
possession by Jun 2027 · Aayush Developers
Aayush Gulmohar
declared completion Dec 2023 · Aayush Builders & Developers LLP
Aayush Poornima
declared completion Dec 2020 · Aayush Developers
Abhilash
declared completion Mar 2022 · Sanjona Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026