MahaRERA Property Intelligence · Raigarh

ADINATH ANMOL

P52000046420 · PUSHPAK, VADGHAR NODE · promoter Shree Riddhi Siddhi

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP52000046420
Registered on22 Jun 2022
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shree Riddhi Siddhi is the promoter of record on 90 projects, of which 7 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
ADINATH ANMOL1G+631 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at PUSHPAK, VADGHAR NODE, SECTOR-1, Thane, Thane, 410206. Per the filed land record, the plot is bounded to the north by PLOT NO 66, to the south by PLOT NO 68, to the east by 15 MTRS WIDE ROAD and to the west by PLOT NO 74 AND 75. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Riddhi Siddhi Constructions is the promoter on 14 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Shree Riddhi Siddhi Constructions project & its RERA track record →

Other flagged projects by Shree Riddhi Siddhi Constructions

Shree Riddhi Siddhi Constructions
FlaggedRaigarh
Shree Riddhi Siddhi Constructions
FlaggedRaigarh
Shree Riddhi Siddhi Constructions
FlaggedRaigarh
Shree Riddhi Siddhi Constructions
FlaggedRaigarh
Shree Riddhi Siddhi Constructions
FlaggedRaigarh
Shree Riddhi Siddhi Constructions
FlaggedRaigarh

Other RERA-registered projects in Panvel

Ambaji Residency
possession by Jul 2026 · Vishal Tukaram Patil
Bayview
possession by Jul 2026 · Skyline Realbuild LLP
Delta Heights
possession by Jul 2026 · Shreenathji Organisers Pvt. Ltd.
Micron Residency
possession by Jul 2026 · Micron Infra
Shree Mahadev Residency
possession by Jul 2026 · SK Developers
Aishwarya Cooperative Housing Society
possession by Aug 2026 · Royal Enterprises

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Adinath Aradhana
declared completion Dec 2021 · Shree Riddhi Siddhi Constructions
Adinath Astha
declared completion Dec 2021 · Shree Riddhi Siddhi Constructions
Adinath Aura
declared completion Dec 2017 · Shree Riddhi Siddhi Constructions
Adinath Crystal
possession by Dec 2028 · Shree Riddhi Siddhi Constructions
Adinath Ganga
declared completion Dec 2023 · Shree Riddhi Siddhi Constructions
Adinath Heights
possession by Dec 2028 · Adhinath Builders And Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026