MahaRERA Property Intelligence · Raigarh

Magnolia Cluster 4

P52000021746 · Wise city · promoter Wadhwa Construction And

Certificate SignedDue 30 Dec 2026

Delivery & Registration

MahaRERA registrationP52000021746
Registered on23 Jul 2019
Promoter-declared completion30 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Wadhwa Construction And is the promoter of record on 60 projects, of which 10 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
Magnolia Cluster 4 - A-431G+2-
Magnolia Cluster 4 - A-441G+2-
Magnolia Cluster 4 - A-451G+2-
Magnolia Cluster 4 - A-461G+2-
Magnolia Cluster 4 - A-471G+2-
Magnolia Cluster 4 - A-481G+2-
Magnolia Cluster 4 - A-491G+2-
Magnolia Cluster 4 - A-501G+2-
Magnolia Cluster 4 - A-511G+2-
Magnolia Cluster 4 - F-381G+2-
Magnolia Cluster 4 - B-231G+2-
Magnolia Cluster 4 - B-171G+2-
Magnolia Cluster 4 - B-181G+2-
Magnolia Cluster 4 - B-191G+2-
Magnolia Cluster 4 - B-201G+2-
Magnolia Cluster 4 - B-211G+2-
Magnolia Cluster 4 - B-221G+2-
Magnolia Cluster 4 - C-161G+2-
Magnolia Cluster 4 - C-231G+2-
Magnolia Cluster 4 - C-171G+2-
Magnolia Cluster 4 - C-181G+2-
Magnolia Cluster 4 - C-191G+2-
Magnolia Cluster 4 - C-201G+2-
Magnolia Cluster 4 - C-211G+2-
Magnolia Cluster 4 - C-221G+2-
Magnolia Cluster 4 - D-141G+2-
Magnolia Cluster 4 - D-151G+2-
Magnolia Cluster 4 - D-161G+2-
Magnolia Cluster 4 - D-171G+2-
Magnolia Cluster 4 - D-181G+2-
Magnolia Cluster 4 - D-131G+2-
Magnolia Cluster 4 - E-181G+2-
Magnolia Cluster 4 - E-191G+2-
Magnolia Cluster 4 - E-201G+2-
Magnolia Cluster 4 - E-211G+2-
Magnolia Cluster 4 - E-221G+2-
Magnolia Cluster 4 - E-171G+2-
Magnolia Cluster 4 - B-241G+2-
Magnolia Cluster 4 - F-231G+2-
Magnolia Cluster 4 - F-241G+2-
Magnolia Cluster 4 - F-251G+2-
Magnolia Cluster 4 - F-261G+2-
Magnolia Cluster 4 - F-271G+2-
Magnolia Cluster 4 - F-281G+2-
Magnolia Cluster 4 - F-221--
Magnolia Cluster 4 - F-291G+2-
Magnolia Cluster 4 - F-301G+2-
Magnolia Cluster 4 - F-311G+2-
Magnolia Cluster 4 - G-231G+2-
Magnolia Cluster 4 - G-241G+2-
Magnolia Cluster 4 - G-251G+2-
Magnolia Cluster 4 - G261G+2-
Magnolia Cluster 4 - G-271G+2-
Magnolia Cluster 4 - G-281G+2-
Magnolia Cluster 4 - C-241G+2-
Magnolia Cluster 4 - D-191G+2-
Magnolia Cluster 4 - F-321G+2-
Magnolia Cluster 4 - F-331G+2-
Magnolia Cluster 4 - F-341G+2-
Magnolia Cluster 4 - F-351G+2-
Magnolia Cluster 4 - F-361G+2-
Magnolia Cluster 4 - F-371G+2-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1250142828/04/2025nitesh kumar vs Wadhwa Construction and Infrastructure Private Limitedorder passed

Location, Land & Connectivity

Located at Wise city, 36 m wide DP road, Kurla, Mumbai Suburban, 410206. Per the filed land record, the plot is bounded to the north by 18 m wide road, to the south by Sector 3, to the east by 12 m wide road and to the west by Plot boundary. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Wadhwa Construction And Infrastructure Private Limited is the promoter on 22 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Wadhwa Construction And Infrastructure Privat project & its RERA track record →

Other flagged projects by Wadhwa Construction And Infrastructure Privat

Wadhwa Construction And Infrastructure Private Limited
FlaggedRaigarh
Wadhwa Construction And Infrastructure Private Limited
FlaggedRaigarh
Wadhwa Construction And Infrastructure Private Limited
FlaggedRaigarh
Wadhwa Construction And Infrastructure Private Limited
FlaggedRaigarh
Wadhwa Construction And Infrastructure Private Limited
FlaggedRaigarh
Wadhwa Construction And Infrastructure Private Limited
FlaggedRaigarh

Other RERA-registered projects in Panvel

Ambaji Residency
possession by Jul 2026 · Vishal Tukaram Patil
Bayview
possession by Jul 2026 · Skyline Realbuild LLP
Delta Heights
possession by Jul 2026 · Shreenathji Organisers Pvt. Ltd.
Micron Residency
possession by Jul 2026 · Micron Infra
Shree Mahadev Residency
possession by Jul 2026 · SK Developers
Aishwarya Cooperative Housing Society
possession by Aug 2026 · Royal Enterprises

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Mahaavir Amber
possession by Dec 2027 · Omprakash Bhanwarlal Chhajer
Mahaavir Exotique Phase I
possession by Dec 2026 · Mahaavir Superstructures Private Limited
Mahaavir Exotique Phase II
possession by Dec 2027 · Mahaavir Superstructures Private Limited
Mahaavir Labdhi Phase 1
possession by Dec 2030 · Mahaavir Buildcon LLP
Mahaavir Majesty - Phase I
declared completion Dec 2019 · Mahaavir Impex
Mahaavir Majesty - Phase II
declared completion Dec 2022 · Mahaavir Impex

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026