MahaRERA Property Intelligence · Palghar

Adiraj status

P99000012749 · Vasai · promoter Shree Adiraj Laxmi

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP99000012749
Registered on07 Sep 2017
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shree Adiraj Laxmi is the promoter of record on 13 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
Adiraj status- A and B wing1G+1430 Dec 2021

Complaints & Orders

4 complaints are on the MahaRERA record for this project, with orders passed in 4. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000004410512/04/2018Arun C Gandhi vs Shree Adiraj Laxmi Builder Pvt. Ltd.order passed
CC00600000002319706/02/2018Aruan G. Saldanha and Godwin A. Saldanha vs M/s. Shree Adiraj Laxmi Builders Pvt. Ltd.order passed
CC00600000007867302/04/2019Kusum G gaud vs M/S Shree Adiraj Laxmi Builders Pvt. Ltd.order passed
CC00600000039708018/08/2023Subhash Dattaram Shinde vs Shree Adiraj Laxmi Builders Pvt. Ltd.order passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202431 Dec 2020Due to market crisis in real estate sectors and financial circumstances of company we are anabel to deliver on said date
31 Dec 202431 Dec 2023we have given possesion date 30/12/2021 but due to pamndemic situation of covid 19 and as per new dcr rules we have revised over approval plan so as we said we are requesting to ma
31 Dec 202431 Dec 2024DELAY IS BECUASE OF NON AVAILABILITY OF LABOUR ON TIME . FOR COMPLETION

Location, Land & Connectivity

Located at Vasai, Vasai, Vasai, Palghar, 401203. Per the filed land record, the plot is bounded to the north by open space, to the south by residential building, to the east by railway line and to the west by residential building. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~33 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ33 km
Powai / Hiranandani business park36 km
Chhatrapati Shivaji Int'l Airport38 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district48 km
Nariman Point / Fort56 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Adiraj Laxmi Builders Pvt. Ltd is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Shree Adiraj Laxmi Builders Pvt. Ltd

Shree Adiraj Laxmi Builders Pvt. Ltd
Past its declared completion dateThane

Other RERA-registered projects in Nallasopara West

Rameshwar
possession by Jul 2026 · Chheda Associate
Shalibhadra Yash
possession by Jul 2026 · Sumatinath Builders
Unique Avenue 210
possession by Aug 2026 · Mangalmurti Land Developers
Shree Ganesh Krupa Residency
possession by Sep 2026 · Nutan Construction CO
Kaneri Heights
possession by Sep 2026 · Shekhar Bhoir AND Others
Aleen Heights
possession by Nov 2026 · AB Builders AND Developers

Other RERA-registered projects in Palghar

Aditi Empire
declared completion Apr 2022 · Rakhumai Developers
Aditi Empire - C Wing
declared completion Apr 2022 · Rakhumai Developers
Aditya Residency
possession by Dec 2027 · Rajesh Sankatha Prasad Shukla
Aditya Residency
possession by May 2029 · Special Developers
Aditya Residency
possession by May 2029 · Ambineon Developers LLP
Aditya Residency
possession by Dec 2029 · Aditi Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026