VIMAL CLASSIC
NALLASOPARA-WEST · OM VIMAL DEVELOPERS
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
26 Dec 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P99000013593
Delivery and registration
When is the project declared for completion?
VIMAL CLASSIC is registered with MahaRERA as P99000013593 and the promoter has declared completion for 26 Dec 2026.
26 Dec 2026
declared completion
3months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P99000013593 |
| Registered on | 16 Oct 2017 |
| Promoter-declared completion | 26 Dec 2026 |
| Current status | Certificate Signed |
| Against today | 3 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VIMAL CLASSIC record 33 quarterly progress reports since registration.
33quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 33 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Om Vimal Developers is the promoter of record on 25 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
25projects
registered with MahaRERA
2flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In VIMAL CLASSIC, ₹40.44 Cr of a declared ₹40.44 Cr estimated project cost is reported as incurred, about 100.0%, as at the last certified filing with MahaRERA.
100.0%
₹40.44 Cr
of ₹40.44 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In VIMAL CLASSIC, 322 of 380 homes filed with MahaRERA are recorded as sold or booked (316 with registered agreements and 6 booked), about 85%, and 58 remain available.
85%sold
322 of 380 homes
₹71.40 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹68.08 Cr (about 95%) is recorded as collected and ₹3.12 Cr as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 322 registered agreements, the effective carpet rate is ₹6,009/sqft, with eight in ten falling between ₹5,169 and ₹7,152 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, home by home
Read from MahaRERA on 16 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 338 homes carry one, and 42 of the 380 are recorded unsold. Since we started watching this ledger, 18 homes have moved out of the unsold list, most recently on 08 September 2026.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| 1 | 442 sqft | Rs 5,889 a sq ft typical, over Rs 4,699 to Rs 7,607 | 31 filed at this size |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.
In VIMAL CLASSIC, 41 of the 42 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25 and 380 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| VIMAL CLASSIC-C | 1 | G+24 | 125 | - |
| VIMAL CLASSIC-D | 1 | G+25 | 125 | - |
| VIMAL CLASSIC-E | 1 | G+21 | 130 | - |
Unit mix on the filing: 349 residential and 31 non-residential (shops/offices).
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 19 Dec 2024 | Because of Covid-19 and unforeseen issue we had phased our project. With D & E as phase-I, Phase-I will be completed before the deadline i.e. Dec.2023. Regarding wing C as Phase-II |
| 19 Dec 2024 | 26 Dec 2026 | Liaison of the Pending Part Environment Permission for the environment clearance for the Bigger layout got delayed by more than 3 years during the COVID period, which is the main r |
Location, Land & Connectivity
Located at NALLASOPARA-WEST, YASHWANT GAURAV COMPLEX,NILEMORE, Borivali, Mumbai Suburban, 401203. Per the filed land record, the plot is bounded to the north by ROAD, to the south by BUILDING, to the east by ROAD and to the west by R G AREA GARDEN. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~34 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Andheri MIDC / SEEPZ | 34 km |
| Powai / Hiranandani business park | 36 km |
| Chhatrapati Shivaji Int'l Airport | 38 km |
| Bandra Kurla Complex (BKC) | 41 km |
| Lower Parel / Worli business district | 48 km |
| Nariman Point / Fort | 56 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.