MahaRERA Property Intelligence · Palghar

Vinay Avenue Building No. 16

P99000053933 · Yashvant Srushti · promoter Amar Associates

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP99000053933
Registered on11 Dec 2023
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Vinay Avenue Building No 16 Wing A1G+7-
Vinay Avenue Building No 16 Wing B1G+7-
Vinay Avenue Building No 16 Wing C1G+4-
Vinay Avenue Building No 16 Wing D1G+4-
Vinay Avenue Building No 16 Wing E1G+4-
Vinay Avenue Building No 16 Wing F1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Yashvant Srushti, 30 W Palghar Boisar Road, Thane, Thane, 401501. Per the filed land record, the plot is bounded to the north by Building No 20 Vinay Residency, to the south by 15 M Wide Internal Road, to the east by 30 MTS WIDE Palghar Boisar Road and to the west by Building No 15 Shanti Vista. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Amar Associates is the promoter on 10 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Amar Associates project & its RERA track record →

Other flagged projects by Amar Associates

Amar Associates
FlaggedMumbai Suburban
Amar Associates
FlaggedMumbai Suburban
Amar Associates
FlaggedMumbai Suburban
Amar Associates
FlaggedMumbai Suburban
Amar Associates
FlaggedMumbai Suburban

Other RERA-registered projects in Boisar

Ostwal Dream Land Phase - II
possession by Jul 2026 · Shree Ostwal Builders LTD
Parvati Homes
possession by Jul 2026 · Iconic Developers
Queens Villa
possession by Jul 2026 · Shashi Kuldeep Ostwal
Classic Apartment
possession by Sep 2026 · I.k.group
Divyajal
possession by Sep 2026 · Divyaraj Properties LLP
Kinjal Complex II
possession by Sep 2026 · Kinjal Enterprises

Major developers building in Boisar

Other RERA-registered projects in Palghar

Vinay Gardens
declared completion Apr 2024 · Vinay Realty
Vinay Unique Corner
declared completion Dec 2019 · Vinayunique Construction Private Limited
Vinay Unique Gardens
declared completion Dec 2019 · Vinayunique Developers
Vinay Unique Heights
declared completion Dec 2019 · SUV Developers
Vinay Unique Homes
declared completion Dec 2019 · Vinayunique Realtors
Vinay Unique Imperia
declared completion Dec 2019 · Imperium Buildcon LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026