MahaRERA Property Intelligence · Raigarh

ADVANCE HARMONY

P52000020840 · SECTOR NO.-50 · promoter Ramesh Dungarshi Shah

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP52000020840
Registered on15 May 2019
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Ramesh Dungarshi Shah is the promoter of record on 2 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
ADVANCE HARMONY1G+431 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at SECTOR NO.-50, DRONAGIRI, Kalyan, Thane, 400702. Per the filed land record, the plot is bounded to the north by 9 MTS WIDE ROAD, to the south by ELECTRICAL SUB STATION, to the east by PLOT NO 133 and to the west by PLOT NO 131. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Ramesh Dungarshi Shah is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Ramesh Dungarshi Shah

Ramesh Dungarshi Shah
FlaggedThane

Other RERA-registered projects in Dronagiri

Astrova
possession by Jul 2026 · Kalpana Sterling Infra LLP
Jupiter Bliss
possession by Sep 2026 · Arjun Ashok Tarachandani
Shree Laxmi Coop Housing Society
possession by Sep 2026 · Mohit Mayuresh Gangal
Siddhivinayak Apartments
possession by Nov 2026 · Baldev Diwan Singh
Phoenix
possession by Dec 2026 · Adarsh Enterprises
Aaradhy Heights
possession by Dec 2026 · Lambodar Infra

Other RERA-registered projects in Raigarh

Advance Kingdom
declared completion Mar 2024 · Advance Home Makers Private Limited
Advik Residency
declared completion Jun 2023 · V Kumar Infratech
Advika Hill City-1
possession by Aug 2026 · M/s Aradhya Developers
Advika Iconic
declared completion Dec 2023 · Sanjay Shankar Chougule
Adwait
possession by Dec 2026 · Venkatesh Developers
Adwaita
declared completion Mar 2022 · Tanaji Balwant Deshmukh

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026