AIKYA HEIGHTS

BYCULLA · AIKYA REALTY PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900026085

Delivery and registration

When is the project declared for completion?

AIKYA HEIGHTS is registered with MahaRERA as P51900026085 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900026085
Registered on15 Aug 2020
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AIKYA HEIGHTS record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Aikya Realty is the promoter of record on 3 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AIKYA HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
AIKYA HEIGHTS1G+1631 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at BYCULLA, MOTISHA CROSS LANE, Mumbai City, Mumbai City, 400027. Per the filed land record, the plot is bounded to the north by ANAND APARTMENT, to the south by SUMER PARK, to the east by MIRZA HUSSAIN AGA SHIRAZEE and to the west by MOTISHAH CROSS LNE. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Aikya Realty PVT LTD is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Aikya Realty PVT LTD

Aikya Realty PVT LTD
FlaggedMumbai City

Other RERA-registered projects in Byculla

Ruparel Vivanza
possession by Mar 2027 · R R Builders
Salsette27 Centre
possession by Mar 2028 · Goodtime Real Estate Development Private
Vida Crest
possession by Dec 2028 · Vida Scapes LLP
Maimoon Tower
Past its declared completion date · declared completion Dec 2022 · Park View Developers
Sanghvi S3 Paradise - Phase 1
declared completion Dec 2021 · Sanghvi Premises Pvt Ltd
Shree Laxmi Residency
declared completion Dec 2021 · Kshitija Infrastructure PVT LTD

Other RERA-registered projects in Mumbai City

Ajinkyatara
declared completion Dec 2017 · Bhalchandra Vinayak Wadnerkar
Ajmal-235
possession by Jul 2029 · Awfi Real Estate Private Limited
Ajmera Downtown
possession by Dec 2027 · Ashjit Realties Pvt. Ltd.
Akanksha
declared completion Dec 2024 · Rupji Constructions
Akanksha
declared completion Jun 2025 · Sugee Ten Developers LLP
Akshay
possession by Dec 2026 · Lalitambika Builders & Developers Pr

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026