Akanksha

Mumbai City · Rupji Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900007380

Delivery and registration

When is the project declared for completion?

Akanksha is registered with MahaRERA as P51900007380 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900007380
Registered on17 Aug 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Akanksha record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Rupji Constructions is the promoter of record on 5 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Akanksha in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
Ankanksha1G+15-

Legal and disputes

What disputes are disclosed?

31 complaints are on the MahaRERA record for Akanksha, with orders passed in 24 of them.

31complaints

24with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005572910/08/2018JOHAR SINGH vs RUPJI CONSTRUCTIONSorder passed
CC00600000005579714/08/2018GHANSHYAM R. HULE vs RUPJI CONSTRUCTIONSorder passed
CC00600000002354701/03/2018VISHAL MANOHAR PATHE vs RUPJI CONSTRUCTIONSorder passed
CC00600000005572709/08/2018TUKARAM NIMBA BILWARE vs RUPJI CONSTRUCTIONSorder passed
CC00600000005573510/08/2018SAYAJIRAO MADHUKAR BORKAR vs RUPJI CONSTRUCTIONSorder passed
CC00600000005573710/08/2018KRISHNA BABURAO REDEKAR vs RUPJI CONSTRUCTIONSorder passed
CC00600000005573910/08/2018MANGESH BABAN NALAWADE vs RUPJI CONSTRUCTIONSorder passed
CC00600000005574110/08/2018NITIN EKNATH JAGTAP vs RUPJI CONSTRUCTIONSorder passed
CC00600000005575711/08/2018RAHUL BABUSHA DUMBRE vs RUPJI CONSTRUCTIONSorder passed
CC00600000005575911/08/2018NITIN SHASHIKANT RASTE vs RUPJI CONSTRUCTIONSorder passed
CC00600000005576011/08/2018VISHAL ABHAY PARKAR vs RUPJI CONSTRUCTIONSorder passed
CC00600000005576111/08/2018SANTOSH TUKARAM LABDE vs RUPJI CONSTRUCTIONSorder passed
CC00600000005576211/08/2018ULHAS DATTARAM PARAB vs RUPJI CONSTRUCTIONSorder passed
CC00600000005578214/08/2018MADHUKAR TATYAJI LOHOKARE vs RUPJI CONSTRUCTIONSorder passed
CC00600000005578814/08/2018DEVENDRA SHRIDHAR SHIRODKAR vs RUPJI CONSTRUCTIONSorder passed
CC00600000005579514/08/2018PANDURANG RADHUJI DHONNAR vs RUPJI CONSTRUCTIONSorder passed
CC00600000005580814/08/2018VILAS PANDURANG BENKE vs RUPJI CONSTRUCTIONSorder passed
CC00600000005581114/08/2018NARENDRA CHINTAMAN PATIL vs RUPJI CONSTRUCTIONSorder passed
CC00600000005581314/08/2018MANGESH ANIL RANE vs RUPJI CONSTRUCTIONSorder passed
CC00600000005591423/08/2018SANDIP A.SONI vs RUPJI CONSTRUCTIONSorder passed
CC00600000019527824/03/2021Adv. Sandeep Vasant Bane vs M/s Rupji Constructionorder passed
CC1250101725/03/2025Dayanand Sahadeo Meshram vs Rupji Constructionspending / no order on file
CC1250121411/04/2025Santaram Mahadev Pawar vs Rupji Constructionsorder passed
CC1250130019/04/2025Varsha Sarang Kedar vs Rupji Constructionsorder passed
CC1250133522/04/2025SURESH LINGAJI PARAB vs Rupji Constructionsorder passed
CC1250137625/04/2025BAPU DATTU SUTAR vs Rupji Constructionspending / no order on file
CC1250142628/04/2025LAXMAN ANANT KAMBLE vs Rupji Constructionspending / no order on file
CC1250143128/04/2025VISHAL MANOHAR PATHE vs Rupji Constructionspending / no order on file
CC1250206124/06/2025DEVENDRA SHRIDHAR SHIRODKAR vs Rupji Constructionspending / no order on file
CC1250230508/07/2025NITIN EKNATH JAGTAP vs Rupji Constructionspending / no order on file
CC1250232109/07/2025SANTOSH TUKARAM LABDE vs Rupji Constructionspending / no order on file

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil CourtEA 4032015Cs Hearing
Consumercc 1212016Final Hearing

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400075. Per the filed land record, the plot is bounded to the north by Existing Building, to the south by CTS 5662pt final plot 311, to the east by Road and to the west by existing water tank. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park4 km
Bandra Kurla Complex (BKC)5 km
Chhatrapati Shivaji Int'l Airport6 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district13 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Rupji Constructions is the promoter on 5 MahaRERA-registered projects, of which 5 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Rupji Constructions

Rupji Constructions
Past its declared completion dateMumbai City
Rupji Constructions
Past its declared completion dateMumbai Suburban
Rupji Constructions
Past its declared completion dateMumbai City
Rupji Constructions
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Ghatkopar East

Mohite Marvel
possession by Sep 2026 · Mohite Realtors LLP
OM Priyadarshani
possession by Sep 2026 · Aakruti Enterprises
Prime Vista
possession by Sep 2026 · Rupvakula Properties Pvt. LTD
Damji Shamji Corporate Square - Wing C
possession by Dec 2026 · Coronate Constructions
Ashirwad CHS LTD
possession by Dec 2026 · Shreedham Developers
Drushti Emerald
possession by Dec 2026 · Samarth Drushti Developers

Other RERA-registered projects in Mumbai City

Akanksha
declared completion Jun 2025 · Sugee Ten Developers LLP
Akshay
possession by Dec 2026 · Lalitambika Builders & Developers Pr
AL Amir Apartment
declared completion Jul 2024 · Janzeb Amirkamal Khan
AL-Madina CHS
possession by Mar 2029 · AR Group Realty
AL Mehdi Heights
declared completion Dec 2023 · AL Haadi Developers
Alankar Building
declared completion Apr 2023 · Prashant Chandrakant Vaidya

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026