Mumbai/Project record

MahaRERA · the public record

Ajmera Heritage - Phase 1

Mumbai Suburban · Offbeat Tech Park LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700011840

Delivery and registration

When is the project declared for completion?

Ajmera Heritage - Phase 1 is registered with MahaRERA as P51700011840 and the promoter has declared completion for 30 Mar 2022.

30 Mar 2022

declared completion

54months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700011840
Registered on31 Aug 2017
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 54 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Ajmera Heritage - Phase 1 record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Offbeat Tech Park is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Ajmera Heritage - Phase 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
A1 Rose A and B1G+430 Mar 2020
A2 Rose C and D1G+430 Mar 2020
A3 Lotus A and B1G+430 Mar 2020
A4 Lotus C and D1G+430 Mar 2020
A5 Jasmine A and B1G+430 Mar 2020
B1 Jasmine C and D1G+430 Mar 2020
C1 Shops Ground and First floor1G+131 Mar 2019

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Ajmera Heritage - Phase 1, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250005306/01/2025Sunita Madhukar Suryavanshi vs Offbeat Tech Park LLPorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 20211. The applicant approached the office of the collector, Thane for the revised N.A. permission. Under its application dated 15/01/2014 and 10/08/2014. The Collector Thane vide its
31 Mar 202131 Mar 20211. The applicant approached the office of the collector, Thane for the revised N.A. permission. Under its application dated 15/01/2014 and 10/08/2014. The Collector Thane vide its

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 411503. Per the filed land record, the plot is bounded to the north by Survey No 28 and 39 and 49, to the south by Government land, to the east by 15 meters wide proposed road and to the west by Government land. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~73 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park73 km
Andheri MIDC / SEEPZ74 km
Chhatrapati Shivaji Int'l Airport78 km
Bandra Kurla Complex (BKC)79 km
Lower Parel / Worli business district88 km
Nariman Point / Fort94 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Thane

Akanksha CO. OP. Hsg. Soc. LTD
possession by Dec 2026 · Krishna Buildcon
Akash Angarika
possession by Jun 2029 · Angarika Buildcon
Akash Deep CHS LTD
possession by Mar 2030 · MV Buildcon
Akash Residency
possession by Jun 2028 · Not Available
Akshar Business Park - Phase II
declared completion Jan 2019 · Akshar Developers
Akshar Elevate
possession by Dec 2031 · Tech Akshar Enterprise LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026