Ajmera Heritage - Phase 1

P51700011840 · promoter Offbeat Tech Park

Certificate SignedDue 30 Mar 2022

Delivery & Registration

MahaRERA registrationP51700011840
Registered on31 Aug 2017
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Offbeat Tech Park is the promoter of record on 2 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
A1 Rose A and B1G+430 Mar 2020
A2 Rose C and D1G+430 Mar 2020
A3 Lotus A and B1G+430 Mar 2020
A4 Lotus C and D1G+430 Mar 2020
A5 Jasmine A and B1G+430 Mar 2020
B1 Jasmine C and D1G+430 Mar 2020
C1 Shops Ground and First floor1G+131 Mar 2019

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1250005306/01/2025Sunita Madhukar Suryavanshi vs Offbeat Tech Park LLPorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Mar 202231 Mar 20211. The applicant approached the office of the collector, Thane for the revised N.A. permission. Under its application dated 15/01/2014 and 10/08/2014. The Collector Thane vide its
30 Mar 202231 Mar 20211. The applicant approached the office of the collector, Thane for the revised N.A. permission. Under its application dated 15/01/2014 and 10/08/2014. The Collector Thane vide its

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 411503. Per the filed land record, the plot is bounded to the north by Survey No 28 and 39 and 49, to the south by Government land, to the east by 15 meters wide proposed road and to the west by Government land. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~73 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park73 km
Andheri MIDC / SEEPZ74 km
Chhatrapati Shivaji Int'l Airport78 km
Bandra Kurla Complex (BKC)79 km
Lower Parel / Worli business district88 km
Nariman Point / Fort94 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Thane

Akanksha CO. OP. Hsg. Soc. LTD
possession by Dec 2026 · Krishna Buildcon
Akankshapurti Chsl
declared completion Dec 2024 · S R Developers
Akash Angarika
possession by Jun 2029 · Angarika Buildcon
Akash Ganga
declared completion May 2023 · Ashish Waman Gole
Akash Residency
possession by Jun 2028 · Not Available
Akshar Alvario
declared completion Nov 2018 · Thalia Akshar Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.