Mumbai/Project record

MahaRERA · the public record

Akshar Business Park - Phase II

Near Turbhe Railway Station · Akshar Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jan 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jan 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700019533

Delivery and registration

When is the project declared for completion?

Akshar Business Park - Phase II is registered with MahaRERA as P51700019533 and the promoter has declared completion for 31 Jan 2019.

31 Jan 2019

declared completion

92months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700019533
Registered on08 Feb 2019
Promoter-declared completion31 Jan 2019
Current statusCertificate Signed
Against todayabout 92 months past the declared date

Promoter record

What else is this promoter on record for?

Akshar Developers is the promoter of record on 38 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

38projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Akshar Business Park - Phase II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Wing Q- Block C1G+503 Nov 2018
Wing R - Block C1G+503 Nov 2018
Wing S - Block c1G+503 Nov 2018
Wing T - Block C1G+503 Nov 2018
Wing U - Block C1G+503 Nov 2018
Wing V - Block C1G+503 Nov 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Near Turbhe Railway Station, Sector 25, Thane, Thane, 400703. Per the filed land record, the plot is bounded to the north by Akshar Business Park- Phase III, to the south by Vashi Turbhe Road, to the east by CWC Complex and to the west by Railway Good Yards. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Akshar Developers is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Vashi

Aurous
possession by Dec 2026 · Asaya Builders AND Developers LLP
Cyber Works
possession by Dec 2026 · Greenscape Ventures
Akshar Panchratna
possession by Jun 2027 · Akshar Dream Homes
Centonic
possession by Jun 2027 · Metro Lifescapes India LLP
Aykon
possession by Dec 2027 · Metro Lifescapes India LLP
Godrej Bayview
possession by Dec 2027 · Suncity Infrastructures LLP

Major developers building in Vashi

Other RERA-registered projects in Thane

Akshar Elevate
possession by Dec 2031 · Tech Akshar Enterprise LLP
Akshar Evanna
declared completion Feb 2024 · M/S Akshar OM Construction
Akshar Evita
declared completion Jun 2021 · M/s.akshar OM Construction
Akshar Panchratna
possession by Jun 2027 · Akshar Dream Homes
Akshata Co-Operative Housing Society Limited
declared completion May 2026 · Sanjiv Surendra Tamhane
Akshita Heights
declared completion Jun 2026 · Akshita Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026