MahaRERA Property Intelligence · Raigarh

AKASHDEEP

P52000030219 · PUSHPAK · promoter North Point Home

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP52000030219
Registered on05 Aug 2021
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, North Point Home is the promoter of record on 24 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 19 homes filed with MahaRERA, 6 are sold/booked and 13 remain available (~32% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹1.14 Cr in agreement value so far. Of that, ₹16.11 Lakh (~14%) is already collected, ₹98.24 Lakh receivable — a read on how far along these sales really are. Note: the project registers 38 homes in total, but this sold/unsold inventory filing covers only 19 of them — the other 19 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 6 registered agreements, the effective carpet rate is ₹12,056/sqft (typical range ₹10,448–₹18,864) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101246 sqft (22.86 sqm)₹22.77 Lakh
Floor 1102172 sqft (16.02 sqm)₹15.96 Lakh
Floor 1104394 sqft (36.57 sqm)₹36.42 Lakh
Floor 1105286 sqft (26.61 sqm)₹26.50 Lakh
Floor 1106249 sqft (23.11 sqm)₹23.02 Lakh
Floor 1107244 sqft (22.67 sqm)₹22.58 Lakh
Floor 2201246 sqft (22.86 sqm)₹22.77 Lakh
Floor 2207244 sqft (22.67 sqm)₹22.58 Lakh
Floor 4402202 sqft (18.78 sqm)₹18.70 Lakh
Floor 4403196 sqft (18.17 sqm)₹18.10 Lakh
Floor 4404249 sqft (23.15 sqm)₹23.06 Lakh
Floor 4405245 sqft (22.77 sqm)₹22.68 Lakh
Floor 4406231 sqft (21.44 sqm)₹21.35 Lakh

⚠ The inventory filing also declares: 19 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5 and 38 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
AKASHDEEP1G+53830 Dec 2023

Unit mix on the filing: 28 residential and 10 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at PUSHPAK, SECTOR 25A, Thane, Thane, 410206. Per the filed land record, the plot is bounded to the north by 9 MTR ROAD, to the south by PLOT NO 283, to the east by 11 MTR ROAD and to the west by PLOT NO 293-294. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~21 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Bandra Kurla Complex (BKC)21 km
Lower Parel / Worli business district22 km
Nariman Point / Fort22 km
Powai / Hiranandani business park23 km
Chhatrapati Shivaji Int'l Airport23 km
Andheri MIDC / SEEPZ26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

North Point Home is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by North Point Home

Other RERA-registered projects in Panvel

Ambaji Residency
possession by Jul 2026 · Vishal Tukaram Patil
Bayview
possession by Jul 2026 · Skyline Realbuild LLP
Delta Heights
possession by Jul 2026 · Shreenathji Organisers Pvt. Ltd.
Micron Residency
possession by Jul 2026 · Micron Infra
Shree Mahadev Residency
possession by Jul 2026 · SK Developers
Aishwarya Cooperative Housing Society
possession by Aug 2026 · Royal Enterprises

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Akruti Residency
declared completion Jun 2023 · Himakshi Akshay Vora
Akshar Edeania
declared completion Dec 2019 · Vagad Constructions
Akshar Emperia Garden
declared completion Dec 2023 · Emperia Realty
Akshar Estonia
declared completion Dec 2021 · Vagad Builders AND Developers Private Li
Akshar Estrella
possession by Mar 2029 · Geomatrix Enterprises LLP
Akshar Rivergate Plot B
declared completion Dec 2025 · Emperia Realty

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026