Mumbai/Project record

MahaRERA · the public record

Ambivali Riveria - Phase - III

karjat · M/S. Ashapura Group

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000015743

Delivery and registration

When is the project declared for completion?

Ambivali Riveria - Phase - III is registered with MahaRERA as P52000015743 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000015743
Registered on22 Mar 2018
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Ambivali Riveria - Phase - III record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ashapura Group is the promoter of record on 58 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

58projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In Ambivali Riveria - Phase - III, 0 of 48 plots filed with MahaRERA are recorded as sold or booked, about 0%, and 48 remain available.

0%sold

0 of 48 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Ambivali Riveria - Phase - III in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at karjat , Ambivali turf Kotalkhalathi , Kurla, Mumbai Suburban, 410201. Per the filed land record, the plot is bounded to the north by River, to the south by Survey 7 and 1 A 7 and 1 B, to the east by Ambivali Riveria Phase I and to the west by Survey 5 and 3. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~62 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park62 km
Bandra Kurla Complex (BKC)65 km
Chhatrapati Shivaji Int'l Airport66 km
Andheri MIDC / SEEPZ66 km
Lower Parel / Worli business district69 km
Nariman Point / Fort70 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Karjat

Dhanlaxmi Heights
possession by Sep 2026 · Dhanlaxmi Developers
Warai Woods Ph 2
Not filing quarterly progress reports · possession by Nov 2026 · Nahar Riddhi Siddhi Developers
Jambrung Valley
possession by Nov 2026 · Kirtiraj Nanasaheb Sawant
Bliss Studio
possession by Dec 2026 · Balsam Builders
Beverly Hills
possession by Dec 2026 · Rudram Infra Projects Private Limited
Jupiter Heights
Not filing quarterly progress reports · possession by Dec 2026 · Jupiter Heights

Major developers building in Karjat

Other RERA-registered projects in Raigarh

Ameya Arcade
declared completion Dec 2024 · Pushpam Infrastructure Developers
Amit Complex
possession by Dec 2028 · Dattaram Dhaku Gawade And Shobha Dattara
Ammara Heights
possession by Dec 2028 · Not Available
Amore
possession by Dec 2027 · Lonare Resort Homes LLP
Amrut Akshat
possession by Dec 2029 · Axat Infrabuild Private Limited
Amrut Dham
possession by Dec 2026 · Shree Ganesh Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026