Mumbai/Project record

MahaRERA · the public record

Ameya Arcade

Sector 17 · Pushpam Infrastructure Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
54registered unitsMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000013131

Delivery and registration

When is the project declared for completion?

Ameya Arcade is registered with MahaRERA as P52000013131 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000013131
Registered on14 Sep 2017
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Ameya Arcade record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Pushpam Infrastructure Developers is the promoter of record on 16 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

16projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In Ameya Arcade, 19 of 24 homes filed with MahaRERA are recorded as sold or booked, about 79%, and 5 remain available.

79%sold

19 of 24 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 54 homes in total, while this sold/unsold inventory filing covers 24 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 111101--
Floor 111102--
Floor 2201--
Floor 7703--
Floor 7704--

The inventory filing also declares: 30 not for sale.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Ameya Arcade in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+28 and 54 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Ameya Arcade1G+285430 Jun 2021

Unit mix on the filing: 40 residential and 14 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020Current Slowdown in Market and Few rectification required are under process
30 Dec 202031 Dec 2024Covid Lockdowns slowed pace of work

Location, Land & Connectivity

Located at Sector 17, Plot no 28, Thane, Thane, 410206. Per the filed land record, the plot is bounded to the north by Plot No 29, to the south by Plot No 27, to the east by 24 mtr road and to the west by Plot No 5. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district20 km
Powai / Hiranandani business park21 km
Nariman Point / Fort21 km
Chhatrapati Shivaji Int'l Airport21 km
Andheri MIDC / SEEPZ24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Arihant Clan Aalishan Phase I
possession by Sep 2026 · Arihant Vatika Realty Private Limited
Balaji Heritage
possession by Sep 2026 · Buildfox Realty LLP
Delta Hills
possession by Sep 2026 · Shree Ganesh Enterprises
Delta Riviera
possession by Sep 2026 · Shreenathji Organisers Pvt. Ltd.
GAJ Oasis
possession by Sep 2026 · Shiv Builders AND Developers
Green View
possession by Sep 2026 · Siddhivinayak Developers

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Amit Complex
possession by Dec 2028 · Dattaram Dhaku Gawade And Shobha Dattara
Ammara Heights
possession by Dec 2028 · Not Available
Amore
possession by Dec 2027 · Lonare Resort Homes LLP
Amrut Akshat
possession by Dec 2029 · Axat Infrabuild Private Limited
Amrut Dham
possession by Dec 2026 · Shree Ganesh Enterprises
Amrut Dhara
possession by Dec 2028 · Shree Ganesh Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.