MahaRERA Property Intelligence · Palghar

Ambrosia Building 8

P99000017064 · Mahim · promoter Pawan Abhimanyu Singh

Certificate SignedDue 30 Sep 2021

Delivery & Registration

MahaRERA registrationP99000017064
Registered on09 Jul 2018
Promoter-declared completion30 Sep 2021
Current statusCertificate Signed
Against todayabout 58 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Pawan Abhimanyu Singh is the promoter of record on 25 projects, of which 12 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Ambrosia Building 81G+731 Mar 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202030 Sep 2021Above project is registered on 09/07/2018 with the expected completion date of 30/09/2020. During the tenure of the project many unexpected hurdles arose which extended the proceed

Location, Land & Connectivity

Located at Mahim, Mahim Road, Palghar, Palghar, 401404. Per the filed land record, the plot is bounded to the north by Building No 1, to the south by Plot No 403, to the east by Building No 7 and to the west by Open Space. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Pawan Abhimanyu Singh is the promoter on 20 MahaRERA-registered projects, of which 11 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Pawan Abhimanyu Singh project & its RERA track record →

Other flagged projects by Pawan Abhimanyu Singh

Pawan Abhimanyu Singh
FlaggedPalghar
Pawan Abhimanyu Singh
FlaggedPalghar
Pawan Abhimanyu Singh
FlaggedPalghar
Pawan Abhimanyu Singh
Past its declared completion datePalghar
Pawan Abhimanyu Singh
FlaggedPalghar
Pawan Abhimanyu Singh
FlaggedPalghar

Other RERA-registered projects in Palghar

Shree SAI Apartment
possession by Jul 2026 · Shree SAI Jivdani Developers
Madhav Vatika - VI
possession by Jul 2026 · R M N H Developers LLP
Prithvi Anand Kuber Complex
possession by Jul 2026 · Prithvi Anand Housing And Land Developer
Vardhaman Divine
possession by Jul 2026 · Vardhaman AND Shah Associates
Symphony Heights
possession by Aug 2026 · Kreate Space LLP
Shree Puram - 2, Building No. 1
possession by Aug 2026 · Vastu Realities

Major developers building in Palghar

Other RERA-registered projects in Palghar

Ameya Villa
declared completion Dec 2024 · Ameya Developers
Ameya Woods
declared completion Dec 2021 · Ameya Squares
Amin Complex
declared completion Mar 2022 · Gajarya Associates
Amin Heritage
possession by Dec 2027 · Crystal Realtors
Amit Palace Chsl
possession by Jul 2029 · SAI Siddhi Builders AND Developers
Amrut YOG
declared completion Mar 2018 · Savita Builders AND Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026