Mumbai/Project record

MahaRERA · the public record

ANANTLEELA COMPLEX

ROHA · DHANAWADE DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Aug 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Aug 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000030675

Delivery and registration

When is the project declared for completion?

ANANTLEELA COMPLEX is registered with MahaRERA as P52000030675 and the promoter has declared completion for 31 Aug 2025.

31 Aug 2025

declared completion

13months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000030675
Registered on08 Sep 2021
Promoter-declared completion31 Aug 2025
Current statusCertificate Signed
Against todayabout 13 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ANANTLEELA COMPLEX record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Dhanawade Developers is the promoter of record on 2 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ANANTLEELA COMPLEX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
ANATLEELA COMPLEX1G+431 Aug 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at ROHA, NANA SHETH ROAD, Roha, Raigarh, 402109. Per the filed land record, the plot is bounded to the north by 9 M WIDE DP ROAD, to the south by SNO 74 2B PLOT NO 2, to the east by S NO 74 2B PLOT NO 2 and to the west by S NO 76 1 A PLOT NO 2. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Roha

AK Platinum Tower
possession by Dec 2026 · Amit Shashikant Khatu
Vardhaman Tower
Not filing quarterly progress reports · possession by Dec 2026 · Vardhaman Tower
Ankit Fiona Phase 2
Not filing quarterly progress reports · possession by Dec 2026 · Mahesh Suhas Padalkar
Chandradarshan Empire Phase II
possession by Dec 2026 · M/S R J Infra Developers
Hecc-SAI City
possession by Dec 2026 · Liyakat Anwar Hafiz
Mithila Icon
possession by Mar 2027 · N R Builders AND Develoeprs

Other RERA-registered projects in Raigarh

Aniruddha LK Crown
possession by Dec 2029 · LK Diwani Infra LLP
Aniruddha Niwas
declared completion Dec 2022 · Arjun Krishnarao Deshmukh
ANJ
declared completion Dec 2021 · Largior Developers Private Limited
Anjali Farms
declared completion Dec 2021 · Largior Developers Private Limited
Ankit Fiona Phase 2
possession by Dec 2026 · Mahesh Suhas Padalkar
Ankita CHS LTD
possession by Sep 2028 · Saigan

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026