MahaRERA · the public record
Anvaya
Charkop · Gagangiri Gargi Construction
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
12 May 2030
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · PR1180002500146
Delivery and registration
When is the project declared for completion?
Anvaya is registered with MahaRERA as PR1180002500146 and the promoter has declared completion for 12 May 2030.
12 May 2030
declared completion
44months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | PR1180002500146 |
| Registered on | 27 Jun 2025 |
| Promoter-declared completion | 12 May 2030 |
| Current status | Certificate Signed |
| Against today | 44 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Anvaya record 4 quarterly progress reports since registration.
4quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 4 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Gagangiri Gargi Construction is the promoter of record on 17 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
17projects
registered with MahaRERA
2flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In Anvaya, ₹7.29 Cr of a declared ₹36.46 Cr estimated project cost is reported as incurred, about 20.0%, as at the last certified filing with MahaRERA.
20.0%
₹7.29 Cr
of ₹36.46 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In Anvaya, 16 of 70 homes filed with MahaRERA are recorded as sold or booked (4 with registered agreements and 12 booked), about 23%, and 54 remain available.
23%sold
16 of 70 homes
₹17.63 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹2.81 Cr (about 16%) is recorded as collected and ₹14.82 Cr as receivable. The project registers 96 homes in total, while this sold/unsold inventory filing covers 70 of them.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 16 registered agreements, the effective carpet rate is ₹16,909/sqft, with eight in ten falling between ₹15,294 and ₹19,467 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, home by home
Read from MahaRERA on 20 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 28 homes carry one, and 42 of the 70 are recorded unsold. Since we started watching this ledger, 23 homes have moved out of the unsold list, most recently on 11 September 2026.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| 1901 | 447 sqft | Rs 75.16 lakh typical, over Rs 68.10 lakh to Rs 86.96 lakh | 15 filed on this stack, floors 3–20 |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.
In Anvaya, 38 of the 42 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21 and 96 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Charkop Gargi Co Op Housing Society Ltd | 1 | G+21 | 96 | - |
Unit mix on the filing: 87 residential and 9 non-residential (shops/offices).
Legal and disputes
What disputes are disclosed?
1 complaint is on the MahaRERA record for Anvaya, with orders passed in 1 of them.
1complaint
1with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| SM12600353 | 25/05/2026 | Bhakti Achrekar vs Gagangiri Gargi Construction | order passed |
Location, Land & Connectivity
Located at Charkop, RDP 4, CTSO Bandra, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by CL-516 and CI-517, to the south by Exiting DP Road, to the east by Plot No. 252 and to the west by Plot No. 256. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Andheri MIDC / SEEPZ | 11 km |
| Powai / Hiranandani business park | 14 km |
| Chhatrapati Shivaji Int'l Airport | 15 km |
| Bandra Kurla Complex (BKC) | 17 km |
| Lower Parel / Worli business district | 24 km |
| Nariman Point / Fort | 32 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.