MahaRERA Property Intelligence · Mumbai Suburban
Aparnavali chsl
P51800014137 · promoter Triveni Developers
Certificate SignedDue 30 Dec 2021
Delivery & Registration
| MahaRERA registration | P51800014137 |
| Registered on | 09 Nov 2017 |
| Promoter-declared completion | 30 Dec 2021 |
| Current status | Certificate Signed |
| Against today | about 55 months past the declared date |
Regulatory Standing
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
- Completion date lapsed — the registered completion date has lapsed without a recorded finish.
- Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.
Builder Track Record
Across MahaRERA, Triveni Developers is the promoter of record on 21 projects, of which 7 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.
| Building | Wings | Floors | Declared completion |
|---|
| Aparnavali Chsl | 1 | G+9 | - |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.
Location, Land & Connectivity
Located at Borivali, Mumbai Suburban, 400092. Per the filed land record, the plot is bounded to the north by FP NO 275, to the south by 1830 mt wide road, to the east by FP NO 275 and to the west by FP NO 275. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
Location & connectivity
The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|
| Andheri MIDC / SEEPZ | 14 km |
| Powai / Hiranandani business park | 17 km |
| Chhatrapati Shivaji Int'l Airport | 17 km |
| Bandra Kurla Complex (BKC) | 20 km |
| Lower Parel / Worli business district | 26 km |
| Nariman Point / Fort | 34 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
Unlock in the ₹999 report →
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
Unlock in the ₹2,999 report →
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Unlock in the ₹999 report →
Should you buy in Aparnavali chsl?
This page is the free MahaRERA filing summary.
The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
✓ Independent — we don't broker these flats✓ Built only from official MahaRERA filings✓ Money-back if it doesn't help your decision
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Builder track record
Triveni Developers is the promoter on 7 MahaRERA-registered projects, of which 6 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:
- THE Borivali Neel Akash Chsl — Past its declared completion date
- New Shiv Krupa Chsl Triveni Contour — Past its declared completion date
- NEW Anamika Triveni Fortune — Past its declared completion date
- Kaveri Apartments Chsl Triveni Eden — Past its declared completion date
- Aparnavali Chsl — Past its declared completion date
- Rishabraj Classic — Past its declared completion date
Other flagged projects by Triveni Developers
Triveni Developers
Past its declared completion dateMumbai Suburban
Triveni Developers
Past its declared completion dateMumbai Suburban
Triveni Developers
Past its declared completion dateMumbai Suburban
Triveni Developers
FlaggedMumbai Suburban
Triveni Developers
Past its declared completion dateMumbai Suburban
Triveni Developers
Past its declared completion dateMumbai Suburban
Other RERA-registered projects in Borivali West
Rishabraj Aradhana
possession by Jul 2026 · H Rishabraj Realty
SBI Ragvihar CHS
possession by Jul 2026 · Tuvin Consultancy LLP
Avyukta Neelkamal
possession by Sep 2026 · Shivoham Associates
Gopal Terrace Co-Operative Housing Society LTD
possession by Sep 2026 · Polo Infra Developers Private Limited
House Of Shreeji Sharan
possession by Sep 2026 · Miles Infra LLP
Sai Signature Spaces
possession by Sep 2026 · Ramachandran Munisawmy Narayan
Major developers building in Borivali West
Other RERA-registered projects in Mumbai Suburban
Apex Green Wood
declared completion Jun 2026 · Apex Infratec
Apna Desh CHS LTD
declared completion Mar 2023 · Vasundhara Builders
Apollo Heights
declared completion Dec 2025 · Jasani Realty Pvt.ltd
Apoorva Rise
declared completion Dec 2024 · Apoorva Housing
Applaud-38
declared completion Dec 2025 · I M Buildcon
APT Plaza
declared completion Aug 2019 · APT Realcon
What to do next (past deadline)
- Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
- Check the MahaRERA portal for a revised completion date or extension order.
- Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
- File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.