Kaveri Apartments chsl Triveni Eden

Borivali West · TRIVENI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800007976

Delivery and registration

When is the project declared for completion?

Kaveri Apartments chsl Triveni Eden is registered with MahaRERA as P51800007976 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800007976
Registered on18 Aug 2017
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Kaveri Apartments chsl Triveni Eden record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Triveni Developers is the promoter of record on 21 projects registered with MahaRERA, 7 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

21projects

registered with MahaRERA

7flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Kaveri Apartments chsl Triveni Eden in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
KAVERI APARTMENTS CHSL TRIVENI EDEN1G+831 Dec 2018

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for Kaveri Apartments chsl Triveni Eden, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019626905/03/2021KEVIN ALFRED PINTO vs M/S. TRIVENI DEVELOPERSorder passed
CC00600000007838510/03/2019Maxim Fernandes vs Triveni Developersorder passed
CC00600000007844913/03/2019Kaveri Apartment CHS Ltd (society) vs Triveni Developersorder passed
CC00600000019296309/03/2020KEVIN PEREIRA vs M/S Triveni Developers through its partner Mr. Mihir Ashok Jethwa and Mr.Ashok A Jethwaorder passed
CC00600000019861713/10/2021Himesh Patel vs Triveni Developerorder passed

A co-operative housing society is recorded as the complainant (Kaveri Apartment CHS Ltd), and MahaRERA has passed an order.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2023DUE TO THE COVID-19 AND CHANGES IN GOVERNMENT POLICY, THE PERMISSIONS ARE BEING DELAYED. THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER

Location, Land & Connectivity

Located at Borivali West , I c colony , Borivali, Mumbai Suburban, 400103. Per the filed land record, the plot is bounded to the north by 6 70 Mtr Road, to the south by cts no 1267, to the east by cts no 1140 and to the west by cts no 1142. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ13 km
Powai / Hiranandani business park16 km
Chhatrapati Shivaji Int'l Airport18 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district28 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Triveni Developers is the promoter on 7 MahaRERA-registered projects, of which 6 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Triveni Developers

Triveni Developers
Past its declared completion dateMumbai Suburban
Triveni Developers
Past its declared completion dateMumbai Suburban
Triveni Developers
Past its declared completion dateMumbai Suburban
Triveni Developers
Past its declared completion dateMumbai Suburban
Triveni Developers
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Borivali West

Borivali Madhumas Chsl
possession by Dec 2026 · Aadhunik Developers
Borivali SAI Hill CHS
possession by Dec 2026 · THE Green Venturez Realtors
Empire Fairmont
possession by Dec 2026 · Empire Realty
Maruti Residency
possession by Dec 2026 · OM Construction
Mascarenhas Apartment
Not filing quarterly progress reports · possession by Dec 2026 · SAI Universal Realtors & Developers
NEW Siddharth CO-Operative Housing Society LTD
possession by Dec 2026 · Not Available

Major developers building in Borivali West

Other RERA-registered projects in Mumbai Suburban

Kaveri Heights
declared completion Dec 2024 · Shree Mishal Sundaram Realty Ventures LL
Kaveri Heritage
possession by Mar 2027 · Kaveri Shine Builders AND Developers LLP
Kaveri Tower
declared completion Dec 2025 · Gnanesh Virendra Lakhia
Kavya Ashwamegh
declared completion Dec 2024 · Kavya Construction Company
Kavya KCD Prestine
possession by Sep 2028 · Kavya KCD Buildcon LLP
KCD Aura
declared completion Dec 2024 · Town KCD Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026