KAVYA ASHWAMEGH

MUMBAI · KAVYA CONSTRUCTION COMPANY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800007183

Delivery and registration

When is the project declared for completion?

KAVYA ASHWAMEGH is registered with MahaRERA as P51800007183 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800007183
Registered on17 Aug 2017
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KAVYA ASHWAMEGH record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Kavya Construction Company is the promoter of record on 10 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KAVYA ASHWAMEGH in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
KAVYA ASHWAMEGH CHSL A WING1G+18-
KAVYA ASHWAMEGH CHSL B WING1G+18-

Legal and disputes

What disputes are disclosed?

6 complaints are on the MahaRERA record for KAVYA ASHWAMEGH, with orders passed in 5 of them.

6complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000004403607/04/2018Yogesh Maru vs Kavya Construction Companyorder passed
CC00600000050040310/05/2024Yogesh Maru vs Kavya Construction Companyorder passed
CC00600000010056417/08/2019Shah Investments vs Kavya Construction Companyorder passed
CC00600000019698913/05/2021Tejas Maniar vs Kavya Construction Companyorder passed
CC00600000040855920/12/2023Rajesh Vinodchandra Shah vs KAVYA CONSTRUCTION COMPANYorder passed
CC1250196016/06/2025Rahul Suresh Belwalkar vs Mr Nimish Manshuklal Vorapending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS
30 Jun 202231 Dec 2024DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 24 MONTHS

Location, Land & Connectivity

Located at MUMBAI, MUMBAI, Mumbai City, Mumbai City, 400075. Per the filed land record, the plot is bounded to the north by Bldg no 17 abutting ground 2 existing Structure, to the south by Abutting 12 20 meter wide road FOS, to the east by Abutting 12 20 meter wide road FOS and to the west by Bldg no 14 abutting ground 2 existing Structure. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park4 km
Bandra Kurla Complex (BKC)5 km
Chhatrapati Shivaji Int'l Airport6 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district13 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghatkopar East

Mohite Marvel
possession by Sep 2026 · Mohite Realtors LLP
OM Priyadarshani
possession by Sep 2026 · Aakruti Enterprises
Prime Vista
possession by Sep 2026 · Rupvakula Properties Pvt. LTD
Damji Shamji Corporate Square - Wing C
possession by Dec 2026 · Coronate Constructions
Ashirwad CHS LTD
possession by Dec 2026 · Shreedham Developers
Drushti Emerald
possession by Dec 2026 · Samarth Drushti Developers

Other RERA-registered projects in Mumbai Suburban

Kavya KCD Prestine
possession by Sep 2028 · Kavya KCD Buildcon LLP
KCD Aura
declared completion Dec 2024 · Town KCD Developers LLP
KCD Jogesh Eva
declared completion Dec 2025 · KCD Heritage Private Limited
KCD Lumin
declared completion Dec 2024 · KCD Heritage Private Limited
KCD Ridgewood
declared completion Sep 2023 · KCD Heritage PVT LTD
Kedar Darshan
possession by Apr 2027 · Kosmos Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026