MahaRERA Property Intelligence · Mumbai Suburban
P51800005989 · promoter Triveni Developers
| MahaRERA registration | P51800005989 |
| Registered on | 14 Aug 2017 |
| Promoter-declared completion | 31 Dec 2023 |
| Current status | Certificate Signed |
| Against today | about 31 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Triveni Developers is the promoter of record on 21 projects, of which 7 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| NEW SHIV KRUPA TRIVENI CONTOUR | 1 | G+22 | 30 Dec 2021 |
25 complaints are on the MahaRERA record for this project, with orders passed in 15. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000000948 | 28/09/2017 | NARENDRA TOTLA vs TRIVENI DEVELOPERS | order passed |
| CC006000000192430 | 03/02/2020 | NIRAJ JAGWANI vs TRIVENI DEVELOPERS | order passed |
| CC006000000193995 | 23/09/2020 | Dr Kamal Kabra & Ramnuj S Kabra & Vimla R Kabra vs Triveni Developer | order passed |
| CC006000000193996 | 23/09/2020 | Kashmira Parish Mehta & Parish Mohanlal Mehta vs Triveni Developers | order passed |
| CC006000000193997 | 23/09/2020 | Mitesh Manohar Rohira & Rakhee M Rohira & Bhavna M Rohira vs Triveni Developers | order passed |
| CC006000000193998 | 23/09/2020 | Pankaj Prabhakar Kadam & Shraddha P Kadam vs Triveni Developers | order passed |
| CC006000000193999 | 23/09/2020 | Ramesh Dharma Dabhilkar & Deepa R Dabhilkar vs Triveni Developers | order passed |
| CC006000000193024 | 14/03/2020 | New Shivkrupa CHS Ltd (society) vs Triveni Developers MIhir A Jethwa Ashok Jethwa | order passed |
| CC006000000194048 | 23/09/2020 | Kishor N Shah vs Triveni Developers | order passed |
| CC006000000196045 | 17/02/2021 | Ritesh Patel vs Triveni Developers | order passed |
| CC006000000199116 | 25/11/2021 | Mr. Himat Amrutlal Joshi, Mr. Mayur Himat Joshi and Mr. Jigar Himat Joshi vs Mr.Mihir A. Jethwa (Partner) M/s- Triveni Developers | order passed |
| CC006000000209595 | 18/01/2022 | JANVI N. JAGWANI vs TRIVENI DEVELOPERS | order passed |
| CC006000000303040 | 14/10/2022 | NAMITA NIRAV MANIAR vs M/S. TRIVENI DEVELOPERS | pending / no order on file |
| CC006000000303043 | 14/10/2022 | VIKRAM VADILAL MANIAR vs M/S. TRIVENI DEVELOPERS | pending / no order on file |
| CC006000000231286 | 26/05/2022 | SANTOSH RAJENDRA PANDA vs MIHIR A JETHWA | order passed |
| CC12501877 | 09/06/2025 | Omkar Dhananjay Patil vs TRIVENI DEVELOPERS | order passed |
| CC12502562 | 25/07/2025 | Lata Gururaja Rao vs TRIVENI DEVELOPERS | order passed |
| CC12504393 | 10/12/2025 | Rakesh Jairam Kavalkar vs TRIVENI DEVELOPERS | pending / no order on file |
| CC12602108 | 10/04/2026 | H RISHABRAJ REALTY through its partner Mr. Harish Ratanchand Jain vs TRIVENI DEVELOPERS | pending / no order on file |
| CC12602110 | 10/04/2026 | H RISHABRAJ REALTY through its partner, Mr. Harish Ratanchand Jain vs TRIVENI DEVELOPERS | pending / no order on file |
| CC12602111 | 10/04/2026 | H RISHABRAJ REALTY through its partner Mr. Harish Ratanchand Jain vs TRIVENI DEVELOPERS | pending / no order on file |
| CC12602112 | 10/04/2026 | H RISHABRAJ REALTY through its partner Harish Ratanchand Jain vs TRIVENI DEVELOPERS | pending / no order on file |
| CC12602113 | 10/04/2026 | H RISHABRAJ REALTY through its partner Mr. Harish Ratanchand Jain vs TRIVENI DEVELOPERS | pending / no order on file |
| CC12602109 | 10/04/2026 | H RISHABRAJ REALTY through its partner Mr. Harish Ratanchand Jain vs TRIVENI DEVELOPERS | pending / no order on file |
| CC12602107 | 10/04/2026 | H RISHABRAJ REALTY through its partner Mr. Harish Ratanchand Jain vs TRIVENI DEVELOPERS | pending / no order on file |
⚠ A co-operative housing society is the complainant here (New Shivkrupa CHS Ltd) and MahaRERA has already passed an order. On a redevelopment, that is the LANDOWNER society in dispute with its developer — a different order of risk from a single buyer's grievance, because it can touch the development rights, the society's consent, and ultimately the title to your flat. Have your lawyer read this order and the development agreement together before you commit.
The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 31 Dec 2023 | 31 Dec 2023 | DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2023 |
| 31 Dec 2023 | 30 Dec 2020 | Due to Lengthy administrative procedure for handing over RG area (Recreation Ground’s area) and additional construction area in lieu of road width FSI policy the project was not a |
Located at Borivali, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by CTS NO 544A, to the south by CTS NO 553A, to the east by 1830 MTR WIDE KULUPWADI ROAD and to the west by CTS NO 550. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Andheri MIDC / SEEPZ | 11 km |
| Powai / Hiranandani business park | 13 km |
| Chhatrapati Shivaji Int'l Airport | 16 km |
| Bandra Kurla Complex (BKC) | 18 km |
| Lower Parel / Worli business district | 26 km |
| Nariman Point / Fort | 34 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in New Shiv Krupa chsl Triveni Contour?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Triveni Developers is the promoter on 7 MahaRERA-registered projects, of which 6 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026