Mumbai/Project record

MahaRERA · the public record

THE BORIVALI NEEL AKASH CHSL

Mumbai Suburban · TRIVENI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800010183

Delivery and registration

When is the project declared for completion?

THE BORIVALI NEEL AKASH CHSL is registered with MahaRERA as P51800010183 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800010183
Registered on24 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for THE BORIVALI NEEL AKASH CHSL record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Triveni Developers is the promoter of record on 21 projects registered with MahaRERA, 7 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

21projects

registered with MahaRERA

7flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for THE BORIVALI NEEL AKASH CHSL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
NEEL AKASH CHSL1G+15-

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for THE BORIVALI NEEL AKASH CHSL, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019373315/08/2020SEETHALAKSHMI HARIHARAN IYER vs TRIVENI DEVELOPERSorder passed
CC00600000019232103/02/2020NIRAJ JAGWANI vs TRIVENI DEVELOPERSorder passed
CC00600000019603915/02/2021Bhalchandra Ganpat Sane vs Triveni Developersorder passed
CC00600000019794102/09/2021PRASAD CHITRE & PALLAVI CHITRE vs M/S TRIVENI DEVELOPERS THROUGH PARTNER MIHIR JETHWA & ASHOK JETHWAorder passed
CC00600000039766530/09/2023RAMESHCHANDRA VENISHANKAR JOSHI vs M/S TRIVENI DEVELOPERS PARTNER MR. ASHOK A. JETHWA AND MR. MIHIR ASHOK JETHWAorder passed

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by MAIN KASTURBA ROAD, to the south by FP NO 77B, to the east by KASTURBA ROAD NO 5 and to the west by KASTURBA ROAD NO 5. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ11 km
Powai / Hiranandani business park13 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)18 km
Lower Parel / Worli business district26 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Triveni Developers is the promoter on 7 MahaRERA-registered projects, of which 6 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Triveni Developers

Triveni Developers
Past its declared completion dateMumbai Suburban
Triveni Developers
Past its declared completion dateMumbai Suburban
Triveni Developers
Past its declared completion dateMumbai Suburban
Triveni Developers
Past its declared completion dateMumbai Suburban
Triveni Developers
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Borivali East

Proposed Redevelopment OF Prakashkunj Chsl
possession by Sep 2026 · Yash Realtors & Developers
Chandratej CHS LTD
possession by Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
possession by Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises
Empire Vrindavan
possession by Nov 2026 · Empire Realty
66 Avenue
possession by Dec 2026 · Parsh Realtors

Major developers building in Borivali East

Other RERA-registered projects in Mumbai Suburban

The Business Hub
declared completion Dec 2025 · Ankur Mayflower Associates
THE Capital
possession by Dec 2027 · ANS Lifestyle Realtors LLP
THE Castle
possession by Aug 2027 · Solidago Realty
THE Chakravarti Ashok Chsl
declared completion Dec 2024 · Orbit Ventures & Co.
The Crimson
possession by Dec 2030 · I M Builtkon Private Limited
The Crown
declared completion Apr 2026 · Elite Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026